Close procurements is a process that involves includes activities for administrative closure such as______________
Correct Answer: B
Explanation/Reference: Explanation: Administrative closure includes step-by-step methodologies that address: actions and activities necessary to satisfy completion or exit criteria for the phase or the project; actions or activities to transfer the products, services, or results to the next phase or to production or operations; and activities to collect project or phase records, audit success or failure, gather lessons learned, and archive information for future use in the organization.