<< Prev Question Next Question >>

Question 666/1011

Which term describes the failure by either the buyer or the seller to perform part or all of the duties of a contract?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (1011q)
Question 1: You are working on identifying possible risks to your projec...
Question 2: An issue log is an input to which Project Human Resource Man...
Question 3: Which type of dependency used in the Sequence Activities pro...
Question 4: Which type of dependency is established based on knowledge o...
Question 5: You are the project manager on a project to improve traffic ...
Question 6: Assume you are working as the project manager on the first p...
Question 7: The cost of nonconformance in a project includes:...
Question 8: The ability to influence cost is greatest during which stage...
Question 9: Life-cycle phase definitions are different in different indu...
Question 10: Who MUST know when a risk event occurs so that a response ca...
Question 11: Motivation is dynamic and complex. The statement, "Motivatio...
Question 12: When is a Salience Model used?
Question 13: Assume on your project you have identified 250 stakeholders ...
Question 14: Perform Integrated Change Control is the process of:...
Question 15: An intentional activity to modify a nonconforming product or...
Question 16: Your company has been awarded a contract for project managem...
Question 17: Activity resource requirements and resource breakdown struct...
Question 18: In which Process Group are lessons learned documented?...
Question 19: You have heard recently that the client calls your progress ...
Question 20: An associate who calculates fees daily to support the depart...
Question 21: In performing human resources functions on a project, which ...
Question 22: The sponsor on the airport runway project has just told the ...
Question 23: Your management has prescribed that a quality audit be condu...
Question 24: Which item is an input to the Define Activities process?...
Question 25: In the Define Activities process, the schedule management pl...
Question 26: Which is a tool or technique used in Define Scope?...
Question 27: Project contracts generally fall into which of the following...
Question 28: You work for a telecommunications company, and when developi...
Question 29: The primary benefit of contract control procurements is to e...
Question 30: The purpose of work performance data in control communicatio...
Question 31: Which of the following is a tool for analyzing a design, det...
Question 32: Even though your project is vastly different from a manufact...
Question 33: What type of contract provides the buyer with the most risk ...
Question 34: You are a Project Manager managing the building of a restaur...
Question 35: What is the definition of project plan execution?...
Question 36: Which risk management strategy seeks to eliminate the uncert...
Question 37: During project selection, which factor is most important?...
Question 38: Which of the following is an output of the Distribute Inform...
Question 39: Which of the following is an example of schedule compression...
Question 40: An element of the project scope statement is:...
Question 41: How should a stakeholder who is classified as high power and...
Question 42: Managing change to the scope baseline is the main objective ...
Question 43: Which output is the approved version of the time-phased proj...
Question 44: You are a Project Manager at Dewey, Cheatum, and Howe and ha...
Question 45: The planned work contained in the lowest level of work break...
Question 46: You are using earned value progress reporting for your curre...
Question 47: Which of the following is an output of a change control syst...
Question 48: What are assigned risk ratings based upon?...
Question 49: Which process occurs within the Monitoring and Controlling P...
Question 50: The Perform Quality Assurance process occurs in which Proces...
Question 51: Communication is important when setting and managing expecta...
Question 52: The project is progressing. As the company starts to release...
Question 53: Which provides the basic framework for managing a project?...
Question 54: Your company decided to award a contract for project managem...
Question 55: A complete set of concepts, terms, and activities that make ...
Question 56: Plan Schedule Management is a process in which Knowledge Are...
Question 57: While processes in the Planning Process Group seek to collec...
Question 58: In complex projects/ initiating processes should be complete...
Question 59: In which Knowledge Area is the project charter developed?...
Question 60: Which characteristic is unique to project work and does not ...
Question 61: The best approach to resolve the settlement of all outstandi...
Question 62: Assume you had a phase gate meeting with your Governance Boa...
Question 63: The Plan Stakeholder Management process belongs to which Pro...
Question 64: Your project has an EV of 100 work-days, an AC of 120 work-d...
Question 65: Which of the following characteristics are found in a functi...
Question 66: One of the objectives of a quality audit is to:...
Question 67: Long-term contracting is an important aspect of project qual...
Question 68: Which of the following is an input into the Develop Project ...
Question 69: Progressively elaborating high-level information into detail...
Question 70: Based on the following metrics: EV=$20,000, AC=$22,000, and ...
Question 71: Updates to organizational process assets such as procurement...
Question 72: When does Monitor and Control Risks occur?...
Question 73: Which of the following is a measure of the value of work com...
Question 74: Recognizing operations management is different than project ...
Question 75: Which is an input to the Verify Scope process?...
Question 76: Project management processes describe project work, while pr...
Question 77: You are beginning a new project staffed with a virtual team ...
Question 78: Which change request is an intentional activity that realign...
Question 79: The component of the human resource management plan that inc...
Question 80: Which process involves documenting the actions necessary to ...
Question 81: Which of the following is a tool and technique for activity ...
Question 82: Which of the following is an input to the Qualitative Risk A...
Question 83: You are managing a project that has five subcontractors. You...
Question 84: A team-building approach that facilitates concurrent enginee...
Question 85: The project team members have gotten together at the end of ...
Question 86: Processes in the Planning Process Group are typically carrie...
Question 87: Calculate the variance for the following: Pessimistic=50, Op...
Question 88: You are managing a project and the sponsor has removed the p...
Question 89: As project manager, you need a relatively fast and informal ...
Question 90: If operations on a work package were estimated to cost $1,50...
Question 91: Which is the document that presents a hierarchical project o...
Question 92: It often is advantageous to appoint a termination manager in...
Question 93: As part of a mid-project evaluation, the project sponsor has...
Question 94: The application of knowledge, skills, tools, and techniques ...
Question 95: There are a number of different earned value management rule...
Question 96: The project scope statement should be used in the identify r...
Question 97: When a backward pass is calculated from a schedule constrain...
Question 98: The principal function of a warranty is to______________...
Question 99: The cumulative CPI has been shown to be relatively stable af...
Question 100: The company is implementing a new project management approac...
Question 101: Which Knowledge Areas include processes from the Closing Pro...
Question 102: Who selects the appropriate processes for a project?...
Question 103: The nature of project work is such that it inevitably causes...
Question 104: The output that defines an approach to increase the support ...
Question 105: What is the term assigned to products or services having the...
Question 106: Which of the following terms indicates a deliverable-oriente...
Question 107: A stakeholder expresses a need not known to the project mana...
Question 108: What are seven consecutive data points on either side of the...
Question 109: Which of the following tools and techniques are utilized in ...
Question 110: What is the total float of the critical path?...
Question 111: Which of the following is an output of the Define Activities...
Question 112: To account for uncertainty in a schedule, reserve analysis m...
Question 113: A watch list of low priority risks is documented in the_____...
Question 114: Quality and credibility of the qualitative risk analysis pro...
Question 115: You are responsible for a project management training curric...
Question 116: The Define Scope process is in which of the following Proces...
Question 117: A risk response strategy that can be used for both threats a...
Question 118: In quality management, the practice "rework" is_____________...
Question 119: Which quality control technique illustrates the 80/20 princi...
Question 120: The performance measurement baseline consists of all the fol...
Question 121: Identify Stakeholders is the process of identifying all of t...
Question 122: The Project Manager is reviewing testing output. Generally, ...
Question 123: In project management, a temporary project can be:...
Question 124: What are the components of the "triple constraint"?...
Question 125: Which document in the project management plan can be updated...
Question 126: Which of the following is an input to the Direct and Manage ...
Question 127: Your organization is characterized by hierarchical organizat...
Question 128: An output of the Create WBS process is:...
Question 129: In which process might you use risk reassessment as a tool a...
Question 130: Job satisfaction, challenging work, and sufficient financial...
Question 131: Assigned risk ratings are based upon:...
Question 132: Assume that you are managing a project team. Your team is on...
Question 133: Which changes occur in risk and uncertainty as well as the c...
Question 134: Which type of graphic is displayed below? (Exhibit)...
Question 135: In the Plan Stakeholder Management process, expert judgment ...
Question 136: The Project Manager is creating an estimate for building a c...
Question 137: To practice effective schedule control, your project team mu...
Question 138: Which of the following is an example of push communication?...
Question 139: Which of the following is an input to Direct and Manage Proj...
Question 140: Which of the following is used to control schedule related i...
Question 141: An example of a group decision-ma king technique is:...
Question 142: During contract negotiations on large contracts, the negotia...
Question 143: You are implementing a project management methodology for yo...
Question 144: The Identify Stakeholders process is found in which Process ...
Question 145: Which of the following is a conflict resolution technique th...
Question 146: The cost baseline and project funding requirements are outpu...
Question 147: If you apply the configuration management system along with ...
Question 148: Fishbone diagrams are also known as what?...
Question 149: Which of the following events would result in a baseline upd...
Question 150: Which of the following are outputs of Develop Project Team?...
Question 151: Budgets reserved for unplanned changes to project scope and ...
Question 152: The business needs, assumptions, and constraints and the und...
Question 153: Which one of the following statements best characterizes an ...
Question 154: Which technique is utilized in the Control Schedule process?...
Question 155: Which item is an example of personnel assessment?...
Question 156: All the following statements are true about the grassroots e...
Question 157: Which items are an output of the Perform Integrated Change C...
Question 158: The basic approach to quality management in projects is to b...
Question 159: Which type of analysis is used to examine project results th...
Question 160: The process of identifying and documenting the specific acti...
Question 161: Which Control Stakeholder Engagement tool or technique allow...
Question 162: During which process does a project manager review all prior...
Question 163: What is the name of a graphic display of project team member...
Question 164: Which stakeholder communicates with higher levels of managem...
Question 165: Six sigma refers to the aim of setting tolerance limits at s...
Question 166: An effective technique for resolving conflict that incorpora...
Question 167: Labor, materials, equipment, and supplies are examples of:...
Question 168: An input to Develop Project Charter is a/an:...
Question 169: Using parametric estimating, if an assigned resource is capa...
Question 170: A primary function of a project management office is to supp...
Question 171: Which of the following is developed from the project scope b...
Question 172: In both the weak and strong matrix organizational structures...
Question 173: A workaround is______________
Question 174: When closing a project, it is a best practice to____________...
Question 175: The risk urgency assessment is a tool and technique used for...
Question 176: For complex procurement items, often contract negotiation ca...
Question 177: The procurement process that documents agreements and relate...
Question 178: The team has implemented a risk response plan when a vendor ...
Question 179: A project manager is appointed full-time to a project and is...
Question 180: Which input to the Manage Stakeholder Engagement process pro...
Question 181: The risk shared between the buyer and seller is determined b...
Question 182: Which of the following are three inputs to the risk register...
Question 183: Which input to the Manage Stakeholder Engagement process is ...
Question 184: The Project Manager and Functional Manager are having a disa...
Question 185: Activity cost estimates are quantitative assessments of the ...
Question 186: You are managing a project in which your team members all wo...
Question 187: A new manufacturing facility is being built for a consumer e...
Question 188: It is important on all projects to determine when and how hu...
Question 189: In organizing a project, a project manager must deal with co...
Question 190: Which process numerically analyzes the effect of identified ...
Question 191: Which Process Group typically consumes the bulk of a project...
Question 192: Which of the following is not a human resources process?...
Question 193: As you prepare your human resource plan, you need to determi...
Question 194: The customer has requested a five-week delay on the project ...
Question 195: The scope of a project cannot be defined without some basic ...
Question 196: Your project is using complex, unproven technology. Your tea...
Question 197: What can a responsibility assignment matrix (RAM) eliminate?...
Question 198: Consider a company that sells products to consumers: as one ...
Question 199: Change requests, project management plan updates, project do...
Question 200: Stakeholder communication requirements should be included as...
Question 201: Procurement documents are used in the identify stakeholder p...
Question 202: When cost variance is negative and schedule variance is posi...
Question 203: Which of the following is a tool or technique of the Define ...
Question 204: Which of the following statements correctly characterizes pu...
Question 205: Funding limit reconciliation is a tool and technique used in...
Question 206: In which process group is the scope first defined?...
Question 207: The project budget is set at $150,000. The project duration ...
Question 208: What are the Project Procurement Management processes?...
Question 209: Which process includes prioritizing risks for subsequent fur...
Question 210: A project manager who communicates to the project team thoug...
Question 211: The printing company is putting a policy in place to use jus...
Question 212: You are in the process of purchasing 67 desktop computers, m...
Question 213: As you are working on your telecommunications project, even ...
Question 214: The close project or phase process addresses actions and act...
Question 215: Which process involves the creation of a document that provi...
Question 216: As you manage the railroad switching station project, you ar...
Question 217: Alternatives generation often is useful in defining project ...
Question 218: Close procurements is a process that involves includes activ...
Question 219: As a result of the control stakeholder expectations process,...
Question 220: You are beginning a new project and a portion of the develop...
Question 221: A Pareto chart is a specific type of:...
Question 222: You are the Project Manager on a cellular bluetooth amplifie...
Question 223: Which type of organizational structure is displayed in the d...
Question 224: Change request status updates are an output of which process...
Question 225: In which Project Management Process Group is the project cha...
Question 226: You are planning a project and want to account for how the p...
Question 227: Prioritizing risks for further analysis or action by assessi...
Question 228: On large contracts, the contract administrator typically has...
Question 229: Inputs to Identifying Stakeholders include:...
Question 230: When a control chart is used to monitor performance of a pro...
Question 231: As the project manager, you have the option of proposing one...
Question 232: An example of an organizational process asset that could aff...
Question 233: Verification of project deliverables occurs during which pro...
Question 234: Which of the following is a tool or technique used in the Ac...
Question 235: The basis of identification for current or potential problem...
Question 236: Which of the following is a means of reaching a group decisi...
Question 237: The database project is approximately 85% complete. The proj...
Question 238: Deming's Fourteen Points provide a way for an organization t...
Question 239: You are working on a new project in your organization. You n...
Question 240: Which of the following schedule network analysis techniques ...
Question 241: What is the estimate at completion (EAC) if the budget at co...
Question 242: Which of the following is an example of contract administrat...
Question 243: A project will be using a vendor to purchase infrastructure ...
Question 244: All of the following are typically part of the project manag...
Question 245: Payment bonds are often required by the contract and require...
Question 246: You are remodeling your kitchen and decide to prepare a netw...
Question 247: The control chart is a tool used primarily to help__________...
Question 248: Which Develop Schedule tool and technique produces a theoret...
Question 249: The e-commerce project is six weeks behind schedule with fiv...
Question 250: Rather than use a WBS, your team developed a bill of materia...
Question 251: An element of the modern quality management approach used to...
Question 252: Work completed, key performance indicators, technical perfor...
Question 253: Recognizing the importance of preparing a stakeholder manage...
Question 254: When large or complex projects are separated into distinct p...
Question 255: Which tool or technique is used in Close Procurements?...
Question 256: Which of the following is an example of recommended correcti...
Question 257: Which process documents the business needs of a project and ...
Question 258: All the following are project baselines that are generally p...
Question 259: The Project Manager has some issues on the team between two ...
Question 260: Organizational theory is a tool used in which Project Human ...
Question 261: Which of the following strategies is used to deal with risks...
Question 262: Float on a Network diagram is also known as:...
Question 263: Which cost is associated with nonconformance?...
Question 264: Which tool or technique is required in order to determine th...
Question 265: The review of a sellers progress toward achieving the goals ...
Question 266: Table reporting, spreadsheet analysis, and presentations are...
Question 267: All the following are examples of project document updates f...
Question 268: Using the three-point estimating technique, if the most like...
Question 269: A change log for communications can be used to communicate t...
Question 270: A risk that arises as a direct result of implementing a risk...
Question 271: As you prepare to close out contracts on your project, you s...
Question 272: Requirements typically are classified into product requireme...
Question 273: How many Project Management Process Groups are there?...
Question 274: You are working on a project to upgrade the existing fiber-o...
Question 275: Which is an example of Administer Procurements?...
Question 276: What is the probability of occurrence if the risk rating is ...
Question 277: Which type of dependency is legally or contractually require...
Question 278: A project team attempts to produce a deliverable and finds t...
Question 279: A project has an EV of 100 workdays, an AC of 120 workdays, ...
Question 280: A risk response strategy in which the project team shifts th...
Question 281: The item that provides more detailed descriptions of the com...
Question 282: Diagram: (Exhibit) If the imposed finish time in question 3 ...
Question 283: As you use the critical chain method in lieu of the critical...
Question 284: In which of the following methods of resolving conflict will...
Question 285: When a seller breaches a contract, the buyer cannot receive_...
Question 286: The key benefit of the Monitoring and Controlling Process Gr...
Question 287: Funding limit reconciliation is a tool and technique of whic...
Question 288: You are using earned value progress reporting for your curre...
Question 289: You are using earned value progress reporting for your curre...
Question 290: If the most likely duration of an activity is five weeks, th...
Question 291: The Project Manager has weekly scheduled status meetings wit...
Question 292: Your project is proceeding according to schedule. You have j...
Question 293: Administer Procurements is part of which Process Group?...
Question 294: Decomposition, rolling wave planning, and templates are all ...
Question 295: Diagram: (Exhibit) What is the duration of the critical path...
Question 296: The purpose of economic value added (EVA) is to_____________...
Question 297: When managing projects, one important technique is capturing...
Question 298: The cumulative cost curve for planned and actual expenditure...
Question 299: Which index is the calculated projection of cost performance...
Question 300: Who determines which dependencies are mandatory during the S...
Question 301: You are project manager on a systems engineering project des...
Question 302: A projects purpose or justification, measurable project obje...
Question 303: Ensuring that projects and programs are reviewed to prioriti...
Question 304: A project can be defined as a:
Question 305: Which process involves aggregating the estimated costs of th...
Question 306: In the Plan Procurement Management process, which source sel...
Question 307: In an organization with a projectized organizational structu...
Question 308: Sample attributes of a communications management plan includ...
Question 309: Monte Carlo is which type of risk analysis technique?...
Question 310: How is the schedule variance calculated using the earned val...
Question 311: The ISO 9000 standards provide______________...
Question 312: Which type of estimating is used to improve the accuracy of ...
Question 313: One output of the control costs process is cost forecasts, w...
Question 314: The project planning is progressing on budget. The Project M...
Question 315: You are in the initial phase of a project and are doing an e...
Question 316: Which tool within the Perform Quality Control process identi...
Question 317: You plan to hold a series of meeting as you execute the proj...
Question 318: Objectives for conducting performance appraisals during the ...
Question 319: In which process is a project manager identified and given t...
Question 320: Organizational process assets, a lessons-learned database, a...
Question 321: Because you are working under a firm-fixed-price contract, m...
Question 322: An output of Control Schedule is:...
Question 323: The process for performing variance analysis may vary, depen...
Question 324: Because your project is slated to last five years, you belie...
Question 325: Diagram: (Exhibit) What is the float for Activity G?...
Question 326: Which one of the following is a key input to the define acti...
Question 327: Which of the following tools and techniques is used in the c...
Question 328: The reason that the cost performance index (CPI) is shown as...
Question 329: Which of the following is a tool and technique for Estimate ...
Question 330: Crosswind Custom Homes is building a customer's dream house....
Question 331: On your project you want to avoid bureaucracy, so you adopt ...
Question 332: A weighting system can be used for all but which one of the ...
Question 333: Conditions that are not under the control of the project tea...
Question 334: A retail expansion project is going relatively well, but the...
Question 335: The Closing Process Group includes which of the following Kn...
Question 336: A Project Manager has completed the Scope Planning process. ...
Question 337: If you decide to follow an open subordination approach to re...
Question 338: Different types of project phases are used on projects, and ...
Question 339: The approaches, tools, and data sources that will be used to...
Question 340: Assume your company is a leader in the market in production ...
Question 341: The project is using a new server that cost $25,000 US. The ...
Question 342: According to Herzberg's Motivator-Hygiene Theory, when achie...
Question 343: Cost aggregation is typically performed by aggregating work ...
Question 344: Scope verification is PRIMARILY concerned with which of the ...
Question 345: Which of the following is an input to Develop Human Resource...
Question 346: Risk categorization is a tool or technique used in which pro...
Question 347: Which conflict resolution technique searches for solutions t...
Question 348: Which technique is commonly used for the Quantitative Risk A...
Question 349: The information technology system for the national power gri...
Question 350: Projects are supposed to succeed, not fail. However, termina...
Question 351: What is the definition of Direct and Manage Project Executio...
Question 352: Projects are undertaken by an organization to support the:...
Question 353: Which of the following is not an example of team development...
Question 354: Activity A has a pessimistic (P) estimate of 36 days, a most...
Question 355: The major difference between the project coordinator and pro...
Question 356: The milestone list is an input to which process from the Pla...
Question 357: Which of the following involves making information available...
Question 358: The Project Manager and team are planning the project. They ...
Question 359: The technique of subdividing project deliverables into small...
Question 360: Plan Risk Management is the process of defining how to:...
Question 361: Project A has a NPV of $275K US over 2.5 years. Project B ha...
Question 362: Thinking back to lessons that your company learned from expe...
Question 363: Which input to the Plan Risk Management process provides inf...
Question 364: The consulting company has created the scope of work for the...
Question 365: A number of items in the stakeholder management plan are sim...
Question 366: Successful project management involves both project leadersh...
Question 367: The team is involved in defining what is needed to ensure pr...
Question 368: Rank ordering of defects should be used to guide corrective ...
Question 369: You are the project manager for the construction of an incin...
Question 370: You are planning to conduct the team-building portion of you...
Question 371: You must consider direct costs, indirect costs, overhead cos...
Question 372: One way to help mitigate personnel risks that may occur duri...
Question 373: What is the lowest level in the Work Breakdown Structure cal...
Question 374: Although the project charter serves to state the project man...
Question 375: The "rule of seven" as applied to statistical process contro...
Question 376: When does risk monitoring and control occur?...
Question 377: Which term describes contract costs that are traceable to or...
Question 378: Stakeholder engagement must be controlled on a continuous ba...
Question 379: Overall cost estimates must be allocated to individual activ...
Question 380: The project will be using a company to provide the technicia...
Question 381: The processes required to establish the scope of the project...
Question 382: Portfolio Management is management of:...
Question 383: All projects involve some extent of change, because they inv...
Question 384: You are working on a project and want to know how many activ...
Question 385: The key management skills required during the adjourning sta...
Question 386: Control charts, flowcharting, histograms, Pareto charts, and...
Question 387: A number of different decision-making styles can be used in ...
Question 388: If the probability of event 1 is 80 percent and of event 2 i...
Question 389: Which process determines the risks that may affect the proje...
Question 390: Which tool or technique allows a large number of ideas to be...
Question 391: The three types of estimates that PERT uses to define an app...
Question 392: You have been a project manager for seven years. You now are...
Question 393: You are the Project Manager on a merger and acquisition proj...
Question 394: Which term is NOT a common name for a procurement document t...
Question 395: A tool and technique used in the Develop Project Charter pro...
Question 396: At the end of the project, what will be the value of SV?...
Question 397: As project manager, you have assembled the team to prepare a...
Question 398: What is the main output of Monitoring and Controlling?...
Question 399: Status of deliverables, implementation status for change req...
Question 400: The most commonly used type of precedence relationship in th...
Question 401: What is the risk rating if the probability of occurrence is ...
Question 402: An input to the Plan Stakeholder Management process is:...
Question 403: As head of the PMO, you will receive performance reports for...
Question 404: Which grid shows which resources are tied to work packages?...
Question 405: One purpose of the communications management plan is to prov...
Question 406: You were assigned recently as the project manager of a progr...
Question 407: The project manager at an organization has just realized tha...
Question 408: Which characteristics do effective project managers possess?...
Question 409: The key inputs to the validate scope process include all the...
Question 410: In the basic communication model, which term refers to the m...
Question 411: Project A is being administered using a matrix form of organ...
Question 412: Which tool and technique of quality planning involves compar...
Question 413: At which stage of the project should certain factors such as...
Question 414: Which type of analysis is used to develop the communications...
Question 415: You are fairly new to managing a project but have been a tea...
Question 416: Which type of managers do composite organizations involve?...
Question 417: Which type of chart is a graphic representation of a process...
Question 418: Which input will be used when tasked with developing the hum...
Question 419: Which of the following is an output of the Monitor and Contr...
Question 420: Which key interpersonal skill of a project manager is define...
Question 421: Which process involves determining, documenting, and managin...
Question 422: Assume you are working on a multi-phase project as your proj...
Question 423: An output of the Validate Scope process is:...
Question 424: Stakeholder satisfaction should be managed as a key project:...
Question 425: The team is involved in defining what is needed to ensure th...
Question 426: The individual or group that provides resources and support ...
Question 427: Projects are separated into phases or subprojects; these pha...
Question 428: Outputs of the Control Communications process include:...
Question 429: Create WBS is part of which of the following Knowledge Areas...
Question 430: Which type of agreement is legal, contractual, and between t...
Question 431: Sensitivity analysis is typically displayed as a/an:...
Question 432: A final project report is a recommended best practice. Altho...
Question 433: Which of the following is an output of the Information Distr...
Question 434: Updates of organizational process assets that are an output ...
Question 435: Having prepared stakeholder management plans on previous pro...
Question 436: Conflicts in which following three areas represent the major...
Question 437: Constant bickering, absenteeism, and substandard performance...
Question 438: Success is measured by benefits realization for a:...
Question 439: A regression line is used to estimate:...
Question 440: Information collected on the status of project activities be...
Question 441: When a project is undertaken to reduce defects in a product ...
Question 442: The project manager for XYZ stationers is sequencing the act...
Question 443: Configuration identification, configuration status accountin...
Question 444: The last step in the stakeholder analysis process is to_____...
Question 445: What type of planning is used where the work to be accomplis...
Question 446: The following is a network diagram for a project. (Exhibit) ...
Question 447: An input to the Identify Risks process is the:...
Question 448: Which of the following is an input to Control Scope?...
Question 449: If you want to calculate the ETC based on your expectations ...
Question 450: The completion of the project scope is measured against the:...
Question 451: Assume that your project in the food service industry involv...
Question 452: An output of the Develop Project Team process is:...
Question 453: Work performance information is an output of which process?...
Question 454: The primary result of effective team development is_________...
Question 455: Your company is in the project management training business....
Question 456: The CPI is .92, and the EV is US$172,500.What is the actual ...
Question 457: Which of the following includes how requirements activities ...
Question 458: Which quality tool incorporates the upper and lower specific...
Question 459: Which Collect Requirements output links the product requirem...
Question 460: You are conducting a stakeholder analysis on your project. A...
Question 461: What is a technique used in the performance reporting proces...
Question 462: Which action should a project manager take to ensure that th...
Question 463: What happens to a stakeholder's project influence over time?...
Question 464: Which type of analysis is used to determine the cause and de...
Question 465: Under which type of contract does the seller receive reimbur...
Question 466: What are the key components of the communication model?...
Question 467: Which cost estimate technique includes contingencies to acco...
Question 468: Which of the following is an example of a risk symptom?...
Question 469: A project you have been managing is falling behind schedule....
Question 470: Buyers use a variety of methods to provide incentives to a s...
Question 471: What type of project structure is a hierarchically organized...
Question 472: Change control procedures, configuration management knowledg...
Question 473: It is critical during the proposal preparation stage that___...
Question 474: Which of the following is not a regulation?...
Question 475: The CPI on your project is 0.84. This means that you should_...
Question 476: Within a matrix organization, dual reporting of team members...
Question 477: On a wireless internet access project, the team is large wit...
Question 478: You have decided to organize a study group of other project ...
Question 479: What are the formal and informal policies, procedures, and g...
Question 480: When painting a bedroom, preparing the walls can be done whi...
Question 481: You are project manager for a systems integration effort and...
Question 482: You are assigned to implement the project control plan. What...
Question 483: Which tool or technique of the Define Activities process all...
Question 484: An input of the Create WBS process is:...
Question 485: You are a personnel management specialist recently assigned ...
Question 486: Forecasts, requested changes, recommended corrective actions...
Question 487: A project team member agrees to change a project deliverable...
Question 488: During which process would stakeholders provide formal accep...
Question 489: Which items are components of a project management plan?...
Question 490: The key to effective cost control is______________...
Question 491: You are working on a construction project in a city differen...
Question 492: You are working on a project that management has decided to ...
Question 493: As a Project Manager you are managing a project that has man...
Question 494: In scope control it is important to determine the cause of a...
Question 495: Which tool and technique identifies inefficient and ineffect...
Question 496: Which Perform Quality Control tool graphically represents ho...
Question 497: Changes to formally controlled documentation, plans, etc. to...
Question 498: The Monitoring and Controlling Process Group includes proces...
Question 499: Change requests are an output from which Project Integration...
Question 500: During which process group is the quality policy determined?...
Question 501: Which type of analysis systemically gathers and analyzes qua...
Question 502: The methodology that combines scope, schedule, and resource ...
Question 503: Which of the following Process Groups covers all Project Man...
Question 504: Which process uses occurrence probability and impact on proj...
Question 505: Analogous cost estimating relies on which of the following t...
Question 506: Which Process Group contains those processes performed to de...
Question 507: The project governance approach should be described in the:...
Question 508: You have decided to award a contract to a seller that has pr...
Question 509: During your project, you will have a number of different typ...
Question 510: Which tool or technique of Plan Quality involves comparing a...
Question 511: A project management office manages a number of aspects incl...
Question 512: Team building should be ongoing throughout the project life ...
Question 513: Which of the following factors contributes the most to team ...
Question 514: What is one of the objectives of Project Risk Management?...
Question 515: Which category of contracts are sellers legally obligated to...
Question 516: The scope management plan and scope baseline are contained i...
Question 517: To which process is work performance information an input?...
Question 518: Often in working as a project manager, it is easy to overloo...
Question 519: Working in the systems integration field, you are primarily ...
Question 520: Quality inspections also may be called______________...
Question 521: Activity A is worth $400, is 95% complete, and actually cost...
Question 522: The Create WBS process is in which of the following Project ...
Question 523: Your quality assurance department recently performed a quali...
Question 524: Which of the following is a narrative description of product...
Question 525: You learn that a former boss of yours who is a PMP has commi...
Question 526: As project manager, you are primarily responsible for implem...
Question 527: A supporting input for controlling stakeholder engagement is...
Question 528: Having worked previously on projects as a team member, you a...
Question 529: The definition of operations is a/an:...
Question 530: Activity A is worth $200, is 100% complete, and actually cos...
Question 531: Which of the following consists of the detailed project scop...
Question 532: A technique used to determine the cause and degree of differ...
Question 533: Requirements documentation will typically contain at least:...
Question 534: What does a CPI value greater than 1.0 indicate?...
Question 535: Which of the following is the primary output of the Identify...
Question 536: The company has been plagued by disorganized projects that a...
Question 537: What is the schedule performance index (SPI) if the planned ...
Question 538: The ways in which the roles and responsibilities, reporting ...
Question 539: Project managers who lead by example and follow through on t...
Question 540: Variance and trend analysis is a tool and technique used in ...
Question 541: A key tool and technique used in define scope is____________...
Question 542: Based on a recent quality audit of your project, your organi...
Question 543: Research has shown that during the execution phase of the pr...
Question 544: Effective communication occurs in groups as well as between ...
Question 545: Which stakeholder approves a project's result?...
Question 546: Project managers for international projects should recognize...
Question 547: Which item is a formal proposal to modify any document, deli...
Question 548: The product scope description is used to:...
Question 549: While working as the project manager on a new project to imp...
Question 550: The project management team has performed earned value analy...
Question 551: As the project progresses, which of the following is routine...
Question 552: The following is a network diagram for a project. (Exhibit) ...
Question 553: Which of the following is an output of the Conduct Procureme...
Question 554: On your project, scope changes, constraints, assumptions, in...
Question 555: You are working on a new project in your city to construct a...
Question 556: Which knowledge area employs the processes required to ensur...
Question 557: Which written document helps monitor who is responsible for ...
Question 558: One of the fundamental tenets of modern quality management s...
Question 559: The total of the planned value (PV) is also known as:...
Question 560: Payback period, return on investment, internal rate of retur...
Question 561: Which of the following is TRUE about most project life cycle...
Question 562: Which process involves monitoring the status of the project ...
Question 563: Calculate the standard deviation for the following: Pessimis...
Question 564: Which of the following are outputs of the Monitor and Contro...
Question 565: Decomposition is a technique used for both WBS development a...
Question 566: What is a deliverable-oriented, hierarchical decomposition o...
Question 567: Which quality tool may prove useful in understanding and est...
Question 568: Which of the following is an information gathering technique...
Question 569: The Human Resource Management processes are:...
Question 570: Which is used to solicit proposals from prospective sellers?...
Question 571: The Project Management Process Group in which performance is...
Question 572: Because risk management is relatively new on projects in you...
Question 573: The project manager needs to review the templates in use. Th...
Question 574: A key member of your project has deep technical skills and m...
Question 575: You are finalizing all the contracts and ensuring that they ...
Question 576: What is the responsibility of the project manager and the fu...
Question 577: Which schedule method allows the project team to place buffe...
Question 578: A purchase order is a good example of which form of contract...
Question 579: What is the difference between the critical path and the cri...
Question 580: You are working on a project with 15 stakeholders. The numbe...
Question 581: Statistical sampling is a method in perform quality control ...
Question 582: Which Process Group's purpose is to track, review, and regul...
Question 583: The probability and impact matrix is primarily used to:...
Question 584: Which is an input to the Scope Verification Process?...
Question 585: For a project to be successful, the project team must do whi...
Question 586: Soft logic is also known as what type of dependency?...
Question 587: The CPI is .92, and the EV is US$172,500. What is the actual...
Question 588: Ensuring that both parties meet contractual obligations and ...
Question 589: The iterative process of increasing the level of detail in a...
Question 590: You are establishing a PMO that will have a project manageme...
Question 591: Which one of the following represents a constraint on the ac...
Question 592: Which enterprise environmental factors are considered during...
Question 593: Which process is responsible for monitoring the status of th...
Question 594: A contract management plan is a subsidiary of what other typ...
Question 595: The diagram below is an example of a: (Exhibit)...
Question 596: What component of the project scope definition defines proje...
Question 597: Information distribution involves making needed information ...
Question 598: To please the customer, a project team member delivers a req...
Question 599: Recently, your company introduced a new processing system fo...
Question 600: If a team member, when facing schedule delays and cost overr...
Question 601: The process to ensure that appropriate quality standards and...
Question 602: The retail chain will be using a vendor to provide engineers...
Question 603: A number of factors affect make-or-buy decisions such as____...
Question 604: Activity resource requirements and the resource breakdown st...
Question 605: The process of conferring with others to come to terms or re...
Question 606: Which Process Group includes the Manage Stakeholder Engageme...
Question 607: Assigning more talented resources to the project to reduce t...
Question 608: Cost baseline is an output of which of the following process...
Question 609: The undistributed budget is part of the______________...
Question 610: A benefit of using virtual teams in the Acquire Project Team...
Question 611: On what is project baseline development established?...
Question 612: What is the number of stakeholders, if the project has 28 po...
Question 613: While preparing the project management plan on a weekly basi...
Question 614: You are leading a team to recommend an equitable reward and ...
Question 615: Inputs to the Define Activities process include:...
Question 616: When writing payment terms in your fixed-price subcontracts ...
Question 617: The cost benefit analysis tool is used for creating:...
Question 618: How is scheduled variance calculated using the earned value ...
Question 619: Which Project Time Management process includes bottom-up est...
Question 620: Which of the following Project Communication Management proc...
Question 621: A Project Manager has been working on quality process of a p...
Question 622: Approved change requests, approved corrective actions, and u...
Question 623: You can use various estimating approaches to determine activ...
Question 624: What type of reward can hurt team cohesiveness?...
Question 625: The following is a network diagram for a project. (Exhibit) ...
Question 626: Although your company's project life cycle does not mandate ...
Question 627: Which schedule compression technique has phases or activitie...
Question 628: An imposed date for completion of the project by the custome...
Question 629: Which process involves identifying and documenting the logic...
Question 630: The project planning is progressing on schedule. The Project...
Question 631: The Process Group that involves coordinating people and reso...
Question 632: As head of the project management office, you need to focus ...
Question 633: Which of the following are placed at selected points in the ...
Question 634: There has been a great delay in waiting to get the charter a...
Question 635: The component of the risk management plan that documents how...
Question 636: During which process would you obtain stakeholders' formal a...
Question 637: Work performance information and cost forecasts are outputs ...
Question 638: The buyer has negotiated a cost-plus-incentive fee contract ...
Question 639: The project has gone smoothly so far. The team members appea...
Question 640: Which standard examines an enterprise's project management p...
Question 641: Which of the following calculations CANNOT be used to determ...
Question 642: Which of the following is an input to the Perform Qualitativ...
Question 643: Which of the following is the best description of configurat...
Question 644: The project manager notes that stakeholders are aware of the...
Question 645: The Project Human Resource Management process that involves ...
Question 646: Managing five contractors on your project for a new stadium ...
Question 647: The process of formalizing acceptance of the completed proje...
Question 648: Which process in Project Time Management includes reserve an...
Question 649: Activity A is worth $300, is 100% complete, and actually cos...
Question 650: A no-cost settlement sometimes is used______________...
Question 651: Which of the following procurement processes results in the ...
Question 652: Your project has a budget of $1.5 million for the first year...
Question 653: You want to minimize the impact of changes on your project, ...
Question 654: Ideally, a project manager should be selected and assigned a...
Question 655: An input to Close Project or Phase is:...
Question 656: You are managing a new technology project designed to improv...
Question 657: You are a project manager leading the construction project o...
Question 658: Another name for an Ishikawa diagram is:...
Question 659: The lowest level normally depicted in a work breakdown struc...
Question 660: When alternative dispute resolution (ADR) is necessary, whic...
Question 661: Because communications planning often is linked tightly with...
Question 662: Which of the following would a Contract Administrator use if...
Question 663: During the stages of team development, your team is in which...
Question 664: The terms strong matrix, balanced matrix, and weak matrix wh...
Question 665: On your systems development project, you noted during a revi...
Question 666: Which term describes the failure by either the buyer or the ...
Question 667: Which of the following inputs is required for the WBS creati...
Question 668: Projects are authorized by which of the following individual...
Question 669: The issue log is useful in control communications because it...
Question 670: Which of the following is an output of the Perform Integrate...
Question 671: A Project Management Office (PMO) manages a number of aspect...
Question 672: Marketplace conditions are an input to which one of the foll...
Question 673: While implementing an approved change, a critical defect was...
Question 674: The company is implementing a quality improvement standard o...
Question 675: You are a Project Manager at Dewey, Cheatum, and Howe and as...
Question 676: Which is the Define Scope technique used to generate differe...
Question 677: Project management processes ensure the:...
Question 678: Which Define Activities tool or technique is used for dividi...
Question 679: Testing falls into which of the following categories of cost...
Question 680: Which tool or technique is used to develop a project charter...
Question 681: The project is going through quality assurance. Which of the...
Question 682: Major difficulties arise when multiple projects need to be m...
Question 683: The team is testing the work of the project and is having is...
Question 684: One of the key benefits of the Plan Human Resource Managemen...
Question 685: The iterative and interactive nature of the Process Groups c...
Question 686: Which tool or technique is used in Manage Stakeholder Expect...
Question 687: The primary benefit of the Plan Schedule Management process ...
Question 688: An output of the Close Project (or Close Phase) process is:...
Question 689: A work package has been scheduled to cost $1,000 to complete...
Question 690: Inputs to the Plan Schedule Management process include:...
Question 691: In order for a matrix organizational approach to be successf...
Question 692: Your organization has decided to use project management for ...
Question 693: In the below path convergence example, if the odds of comple...
Question 694: All of the following are objectives of a quality audit______...
Question 695: An input to the Perform Quantitative Risk Analysis process i...
Question 696: A conflict resolution approach that is NOT considered to be ...
Question 697: As a Project Manager, your first priority is to accomplish t...
Question 698: The project scope statement addresses and documents all the ...
Question 699: Crosswind Custom Homes is building a customer's dream house....
Question 700: At which point of the project is the uncertainty the highest...
Question 701: Risk mitigation involves______________...
Question 702: Which type of risk diagram is useful for showing time orderi...
Question 703: Contested changes are requested changes when the buyer and s...
Question 704: As the buyer is involved in creating request for proposals (...
Question 705: Your cost control specialist has developed a budget plan for...
Question 706: Assume your stakeholder management plan has been approved. Y...
Question 707: Which of the following types of a dependency determination i...
Question 708: As you work on your project to update its software training ...
Question 709: The process of monitoring the status of the project and prod...
Question 710: Which tool is used to develop technical details within the p...
Question 711: You are managing a project with team members located at cust...
Question 712: What is the schedule performance index (SPI) using the follo...
Question 713: Project execution must be compared, and deviations must be m...
Question 714: Which process is conducted from project inception through co...
Question 715: Which of the following is a tool and technique used to monit...
Question 716: Which basic quality tool is most useful when gathering attri...
Question 717: On a large medical billing system project, the team is large...
Question 718: The e-commerce project has gone well other than the fact tha...
Question 719: The Perform Integrated Change Control process occurs in whic...
Question 720: Which of the following is a schedule network analysis techni...
Question 721: Which process involves aggregating the estimated costs of th...
Question 722: You have been assigned as the project manager for a major pr...
Question 723: You finally have been appointed project manager for a major ...
Question 724: Analytical techniques are a tool and technique of which proc...
Question 725: The project has a current cost performance index of 0.80. As...
Question 726: A project manager providing information to the right audienc...
Question 727: The project is nearing completion. The team is involved in a...
Question 728: Cost of quality (COQ) refers to total cost of/to:...
Question 729: Which of the following methods is a project selection techni...
Question 730: The process improvement plan details the steps for analyzing...
Question 731: Schedule milestones and a predefined budget are examples of:...
Question 732: Which of the following best relates to unknown unknowns?...
Question 733: The sponsor plays a key role in project success. Which of th...
Question 734: When you review cost performance data on your project, diffe...
Question 735: Based on the following metrics: EV= $20,000, AC= $22,000, an...
Question 736: Power, urgency, and legitimacy are attributes of which stake...
Question 737: Which of the following change requests can bring expected fu...
Question 738: Modifications may be needed to the WBS and WBS dictionary be...
Question 739: The project charter is an input to which process?...
Question 740: Crosswind Custom Homes is building a customer's dream house....
Question 741: The degree, amount, or volume of risk that an organization o...
Question 742: A project requires a component with well-understood specific...
Question 743: Reserve analysis is a tool and technique used in which proce...
Question 744: Your firm specializes in roller-coaster construction. It rec...
Question 745: An output of the Plan Quality Management process is:...
Question 746: In project communications, the first step in a written commu...
Question 747: The process of obtaining seller responses, selecting a selle...
Question 748: Which of the following is a key input to define activities?...
Question 749: An input to the Collect Requirements process is the:...
Question 750: The chances for successful completion of a multidisciplinary...
Question 751: During a bidders conference, it is important that___________...
Question 752: Resource calendars are included in the:...
Question 753: Which statement correctly describes the value of a business ...
Question 754: Improvement to the processes and the product is a goal of pr...
Question 755: The Project Manager is involved in acquiring the project tea...
Question 756: Which of the following investigates the likelihood that each...
Question 757: Today, the primary cause of why projects are not completed o...
Question 758: Which of the following is a tool or technique for the Plan P...
Question 759: Which of the following formulas calculates the number of com...
Question 760: A tool and technique used during the Define Scope process is...
Question 761: Statements of organizational policies and philosophies, posi...
Question 762: The person assigned by the performing organization to be res...
Question 763: The project is very challenging and has been very trying on ...
Question 764: What is a tool to improve team performance?...
Question 765: The end point of a project phase can be referred to as:...
Question 766: Organizational planning impacts projects by means of project...
Question 767: Which tool or technique used in the Control Procurements pro...
Question 768: Collecting requirements is critical in project scope managem...
Question 769: To which process is work performance information an input?...
Question 770: A disadvantage associated with virtual teams is that they:...
Question 771: Which document describes the necessary information to determ...
Question 772: Project managers should pay attention to critical and subcri...
Question 773: Who provides the inputs for the original estimates of activi...
Question 774: Which technique is utilized in the Schedule Control process?...
Question 775: The team is in the process of validating that the quality pl...
Question 776: A project manager requesting industry groups and consultants...
Question 777: Activity cost estimates and the project schedule are inputs ...
Question 778: The degree of uncertainty an entity is willing to take on in...
Question 779: Which document defines how a project is executed, monitored ...
Question 780: Assume you have identified your stakeholders and are prepari...
Question 781: In some cases, contract termination refers to______________...
Question 782: Correlated and contextualized information on how closely the...
Question 783: Your project has been under way for some time, but indicator...
Question 784: Which organizational process assets update is performed duri...
Question 785: Ranking risks is performed in which of the following?...
Question 786: The greatest degree of uncertainty is encountered during whi...
Question 787: A purchase order for a specified item to be delivered by a s...
Question 788: A Project Manager is assigned to a project that is in the co...
Question 789: Two key inputs to the perform quantitative risk analysis pro...
Question 790: Your project manager has requested that you provide him with...
Question 791: A number of items may be part of the schedule data for the p...
Question 792: The IT initiative project is on schedule and under budget. T...
Question 793: You work as a project manager in the largest hospital in the...
Question 794: Diagram: (Exhibit) If a project planner imposes a finish tim...
Question 795: You are the Project Manager for a national satellite rollout...
Question 796: In the Initiating Process Group, at what point does the proj...
Question 797: The WBS represents all product and project work, including p...
Question 798: You are a member of a project selection committee that uses ...
Question 799: Within project integration management, the statement of work...
Question 800: The purpose of using what-if analysis in schedule control is...
Question 801: Which of the following is an input to Direct and Manage Proj...
Question 802: As you prepare to close your project, which of the following...
Question 803: Which of the following is a group decision-making technique?...
Question 804: In which type of contract are the performance targets establ...
Question 805: Two people at work are discussing roles and responsibilities...
Question 806: Inputs to the Plan Risk Management process include the:...
Question 807: The project is progressing well but has begun to experience ...
Question 808: A number of approaches can be helpful when estimating resour...
Question 809: Lessons learned are created and project resources are releas...
Question 810: Which of the following choices is a contract closure tool or...
Question 811: Risk responses reflect an organization's perceived balance b...
Question 812: The Process Group in which the internal and external stakeho...
Question 813: The following chart contains information about the tasks in ...
Question 814: In a construction project schedule, what is the logical rela...
Question 815: Identifying interrelationships and potential overlap between...
Question 816: The baseline for evaluating whether requests for changes or ...
Question 817: The reason that the schedule performance index (SPI) is show...
Question 818: What is a hierarchically organized depiction of the identifi...
Question 819: Which of the following is an example of the simplest fixed-p...
Question 820: As of the fourth month on the Acme project, cumulative plann...
Question 821: PMBOI Guide is a standard that describes:...
Question 822: Your role in the project includes helping to resolve problem...
Question 823: A Project Manager has been working on quality process of a p...
Question 824: All the following are outputs of the estimate cost process E...
Question 825: Technical capability, past performance, and intellectual pro...
Question 826: Which of the following response strategies are appropriate f...
Question 827: The process of identifying and documenting relationships amo...
Question 828: Which of the following correctly describes when organization...
Question 829: What is the typical role of senior management on a project?...
Question 830: The project team should have a working knowledge of statisti...
Question 831: The scope management plan and scope baseline are contained i...
Question 832: Which process develops options and actions to enhance opport...
Question 833: The following chart contains information about the tasks in ...
Question 834: The risk register may need to be updated as an output of whi...
Question 835: A number of organizational process assets are useful as inpu...
Question 836: Functional managers play a vital role in ensuring project su...
Question 837: Which of the following buffers protects the target finish da...
Question 838: Most statistical simulations of budgets, schedules, and reso...
Question 839: Co-location is a tool and technique of:...
Question 840: Which element does a project charter contain?...
Question 841: Which risk response strategy is common for both positive and...
Question 842: Your approved project schedule was based on resource levelin...
Question 843: Types of internal failure costs include:...
Question 844: Which of the following is an output of Direct and Manage Pro...
Question 845: The scope management plan is a subsidiary of which project d...
Question 846: Which of the following is an output of Define Scope?...
Question 847: Projects that share common outcomes, collective capability, ...
Question 848: The process of identifying and documenting project roles, re...
Question 849: Which type of manager is assigned by the performing organiza...
Question 850: As project manager, you plan to conduct a "kickoff" meeting ...
Question 851: Perform Quality Control is accomplished by:...
Question 852: In defining a milestone, which of the following is correct?...
Question 853: Which tool or technique is used in the Plan Scope Management...
Question 854: Which stakeholder classification model groups stakeholders b...
Question 855: Which of the following risk response strategies involves all...
Question 856: Which of the following statements is true regarding project ...
Question 857: To meet regulatory requirements, you need to crash your proj...
Question 858: The pilot for PM Airlines is in the process of flying from D...
Question 859: Which type of project management office (PMO) supplies templ...
Question 860: The estimate costs process uses all the following tools and ...
Question 861: Which of the following is an input of the Define Activities ...
Question 862: In project development, schedule information such as who wil...
Question 863: Project quality management was once thought to include only ...
Question 864: Tools and techniques used to perform quality assurance inclu...
Question 865: Plan-do-check-act is also known as:...
Question 866: Impacts to other organizational areas, levels of service, an...
Question 867: Which of the following would a team create as a result of us...
Question 868: When you are about to terminate a contract, the one place to...
Question 869: You are leading a team to review and improve the project sel...
Question 870: The organization's perceived balance between risk taking and...
Question 871: The project is in a projectized environment. There are signi...
Question 872: Which illustrates the connection between work that needs to ...
Question 873: Assume you are managing a project, and your project manageme...
Question 874: Oftentimes when a project is terminated, senior managers wil...
Question 875: You have a number of costs to track and manage because your ...
Question 876: An input to the Perform Integrated Change Control process is...
Question 877: You are the Project Manager for a high speed data communicat...
Question 878: An input to the Create WBS process is a:...
Question 879: Validate scope works hand-in-hand with control quality and g...
Question 880: Although your project team is working virtually, you are str...
Question 881: You are working on a contract in a remote location. The cont...
Question 882: Which is an enterprise environmental factor?...
Question 883: On the electric company project the government implemented a...
Question 884: Expert judgment is a best practice as a tool and technique i...
Question 885: The following chart contains information about the tasks in ...
Question 886: In defining a risk trigger, which of the following is most a...
Question 887: The plan quality management process includes all the followi...
Question 888: Which process group contains the processes performed to fina...
Question 889: A tool and technique used during the Create WBS process is:...
Question 890: During what process is the quality policy determined?...
Question 891: An input to the Plan Procurement Management process is:...
Question 892: A strengths, weaknesses, opportunities, and threats (SWOT) a...
Question 893: You are a Project Manager managing the building of a housing...
Question 894: Which Define Activities output extends the description of th...
Question 895: Activities on the critical path have which type of float?...
Question 896: Managing ongoing production of goods and services to ensure ...
Question 897: The project team is developing rules for reporting status on...
Question 898: Which estimating technique uses the actual costs of previous...
Question 899: You are conducting a stakeholder analysis on your project. Y...
Question 900: Which technique is commonly used for the Perform Quantitativ...
Question 901: The direct and manage project work process truly is importan...
Question 902: Project deliverables are the outputs that include the produc...
Question 903: Stakeholders often have issues, and you have asked each of y...
Question 904: Assume that you were the first person in your company to be ...
Question 905: Validate scope______________
Question 906: A car company authorized a project to build more fuel-effici...
Question 907: In the Estimate Activity Durations process, productivity met...
Question 908: The Project Manager is creating an estimate for building a c...
Question 909: Which of the following are examples of interactive communica...
Question 910: Which of the following types of contracts has the least risk...
Question 911: You work for a software development company that has followe...
Question 912: The project scope statement and resource calendars are input...
Question 913: There are three uses and types of Pareto analysis. If you wi...
Question 914: Having worked previously as a software project manager, you ...
Question 915: Which of the following is a complete set of indexed contract...
Question 916: The project management processes presented in the PMBOK Guid...
Question 917: Which of the following is a schematic display of the project...
Question 918: Which of the following makes changes to formally control doc...
Question 919: Project Management Process Groups are linked by:...
Question 920: Which Project Management Process Group includes Collect Requ...
Question 921: A project manager should document the escalation path for un...
Question 922: The highest risk impact generally occurs during which one of...
Question 923: You are the project manager for a major logistics installati...
Question 924: The team you have organized for your new project consists of...
Question 925: The project planning for the trade show is progressing on sc...
Question 926: At the time the risk register is first prepared, it should c...
Question 927: A Project Manager has been assigned to manage a project to d...
Question 928: As a project manager, not only must you be a leader, but you...
Question 929: Managing procurement relationships and monitoring contract p...
Question 930: You are the project manager for a two-year project that is n...
Question 931: Those who enter into a contractual agreement to provide serv...
Question 932: Which type of probability distribution is used to represent ...
Question 933: Your project management office implemented a project managem...
Question 934: Which technique is used in Perform Quantitative Risk Analysi...
Question 935: Project managers spend a great deal of time communicating wi...
Question 936: An input to the Plan Cost Management process is:...
Question 937: Analyzing the strengths, weaknesses, opportunities, and thre...
Question 938: The only Process Group that comprises processes that typical...
Question 939: You are a Project Manager who is involved in the procurement...
Question 940: The process of developing a detailed description of the proj...
Question 941: The Project Manager is working with the customer to gain for...
Question 942: The key benefit of the control communications process is to_...
Question 943: Which can be used to determine whether a process is stable o...
Question 944: High-level project risks are included in which document?...
Question 945: Taking out insurance in relation to risk management is calle...
Question 946: Which process is included in the Project Integration Managem...
Question 947: You are the Project Manager on a project where $4M US will b...
Question 948: The software development company has recently been awarded a...
Question 949: Stakeholders can be identified in later stages of the projec...
Question 950: One of the tools and techniques of the Manage Project Team p...
Question 951: The purpose of the Project Communications Management Knowled...
Question 952: A number of tools and techniques are helpful in the perform ...
Question 953: The stakeholder register should not be prepared only one tim...
Question 954: Which following item is NOT an input to control scope?...
Question 955: An output of the Manage Project Team process is:...
Question 956: Organizational process assets can be divided into which of t...
Question 957: You are developing a project charter and want to ensure that...
Question 958: Historical information is used______________...
Question 959: Which tool or technique is an examination of industry and sp...
Question 960: (Exhibit) Which of the following is the correct network diag...
Question 961: A weighting system is a tool for which area of procurement?...
Question 962: Which of the following is an output of the Plan Quality proc...
Question 963: The integrative nature of project management requires which ...
Question 964: You are managing a complex project for a new method of heati...
Question 965: The project planning is progressing. The team has involved t...
Question 966: Stakeholder engagement involves a number of critical activit...
Question 967: The specific technique for identifying a problem, discoverin...
Question 968: Any step recommended to bring expected future performance in...
Question 969: The process of establishing the policies, procedures, and do...
Question 970: In the initial stage of the project life cycle, the project'...
Question 971: The process of defining how the project scope will be valida...
Question 972: Increased attention to return on investment (ROI) now requir...
Question 973: The process of identifying specific actions to be performed ...
Question 974: Skills necessary for project management such as motivating t...
Question 975: Activity A has a duration of three days and begins on the mo...
Question 976: The sponsor is a key project stakeholder because he or she__...
Question 977: The project will be using a company to provide the technicia...
Question 978: In Plan Risk Management, which of the management plans deter...
Question 979: Units of measure, level of precision, level of accuracy, con...
Question 980: The area where the project manager can have the greatest imp...
Question 981: Project deliverables that have been completed and checked fo...
Question 982: You are a project manager for residential construction. As a...
Question 983: Which Manage Communications tool or technique focuses on ide...
Question 984: Which of the following tools and techniques is used to estim...
Question 985: You have assembled a core team to develop the project manage...
Question 986: Within your company's portfolio, your project is ranked in t...
Question 987: An approach to provide insight into the health of the projec...
Question 988: Assume you have been working with your sponsor to prepare yo...
Question 989: The key way for a project manager to promote optimum team pe...
Question 990: Which type of control tool identifies whether or not a proce...
Question 991: Assume that your actual costs are $800; your planned value i...
Question 992: Which schedule network analysis technique modifies the proje...
Question 993: When addressing roles and responsibilities,which item ensure...
Question 994: When a permitting agency takes longer than planned to issue ...
Question 995: An input required in Define Scope is an organizational:...
Question 996: Through whom do project managers accomplish work?...
Question 997: Which of the following is an enterprise environmental factor...
Question 998: The project is progressing well but has begun to experience ...
Question 999: The project scope baseline should be used in the identify ri...
Question 1000: Tools and techniques used in Direct and Manage Project Work ...
Question 1001: Which of the following correctly lists the configuration man...
Question 1002: Tools and techniques used for Plan Communications include th...
Question 1003: The zero duration of milestones in project planning occurs b...
Question 1004: When you established the change control board for your avion...
Question 1005: Requirements for formal deliverable acceptance are defined i...
Question 1006: Which process involves user cost estimates and the schedule ...
Question 1007: The project scope statement is important in scope control be...
Question 1008: What is used to define the accounts that the WBS and organiz...
Question 1009: Your company is embarking on a project to launch a new produ...
Question 1010: The contract in which the seller is reimbursed for all allow...
Question 1011: A special type of bar chart used in sensitivity analysis for...