Project execution must be compared, and deviations must be measured for management control according to the______________
Correct Answer: B
Explanation/Reference: Explanation: The PMB is an approved, integrated scope-schedule-cost plan for the project work against which project execution is compared in order to measure and manage performance. It includes contingency reserve but not management reserve. It typically integrates scope, schedule, and cost parameters of the project, but it may also include technical and quality parameters.