Question 288/1011

You are using earned value progress reporting for your current project in an effort to teach your software developers the benefits of earned value. You plan to display project results on the cafeteria bulletin board so that the team knows how the project is progressing.
PV = $2,200
EV = $2,000
AC = $2,500
BAC = $10,000
What is the EAC for this project, and what does it represent?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (1011q)
Question 1: You are working on identifying possible risks to your projec...
Question 2: An issue log is an input to which Project Human Resource Man...
Question 3: Which type of dependency used in the Sequence Activities pro...
Question 4: Which type of dependency is established based on knowledge o...
Question 5: You are the project manager on a project to improve traffic ...
Question 6: Assume you are working as the project manager on the first p...
Question 7: The cost of nonconformance in a project includes:...
Question 8: The ability to influence cost is greatest during which stage...
Question 9: Life-cycle phase definitions are different in different indu...
Question 10: Who MUST know when a risk event occurs so that a response ca...
Question 11: Motivation is dynamic and complex. The statement, "Motivatio...
Question 12: When is a Salience Model used?
Question 13: Assume on your project you have identified 250 stakeholders ...
Question 14: Perform Integrated Change Control is the process of:...
Question 15: An intentional activity to modify a nonconforming product or...
Question 16: Your company has been awarded a contract for project managem...
Question 17: Activity resource requirements and resource breakdown struct...
Question 18: In which Process Group are lessons learned documented?...
Question 19: You have heard recently that the client calls your progress ...
Question 20: An associate who calculates fees daily to support the depart...
Question 21: In performing human resources functions on a project, which ...
Question 22: The sponsor on the airport runway project has just told the ...
Question 23: Your management has prescribed that a quality audit be condu...
Question 24: Which item is an input to the Define Activities process?...
Question 25: In the Define Activities process, the schedule management pl...
Question 26: Which is a tool or technique used in Define Scope?...
Question 27: Project contracts generally fall into which of the following...
Question 28: You work for a telecommunications company, and when developi...
Question 29: The primary benefit of contract control procurements is to e...
Question 30: The purpose of work performance data in control communicatio...
Question 31: Which of the following is a tool for analyzing a design, det...
Question 32: Even though your project is vastly different from a manufact...
Question 33: What type of contract provides the buyer with the most risk ...
Question 34: You are a Project Manager managing the building of a restaur...
Question 35: What is the definition of project plan execution?...
Question 36: Which risk management strategy seeks to eliminate the uncert...
Question 37: During project selection, which factor is most important?...
Question 38: Which of the following is an output of the Distribute Inform...
Question 39: Which of the following is an example of schedule compression...
Question 40: An element of the project scope statement is:...
Question 41: How should a stakeholder who is classified as high power and...
Question 42: Managing change to the scope baseline is the main objective ...
Question 43: Which output is the approved version of the time-phased proj...
Question 44: You are a Project Manager at Dewey, Cheatum, and Howe and ha...
Question 45: The planned work contained in the lowest level of work break...
Question 46: You are using earned value progress reporting for your curre...
Question 47: Which of the following is an output of a change control syst...
Question 48: What are assigned risk ratings based upon?...
Question 49: Which process occurs within the Monitoring and Controlling P...
Question 50: The Perform Quality Assurance process occurs in which Proces...
Question 51: Communication is important when setting and managing expecta...
Question 52: The project is progressing. As the company starts to release...
Question 53: Which provides the basic framework for managing a project?...
Question 54: Your company decided to award a contract for project managem...
Question 55: A complete set of concepts, terms, and activities that make ...
Question 56: Plan Schedule Management is a process in which Knowledge Are...
Question 57: While processes in the Planning Process Group seek to collec...
Question 58: In complex projects/ initiating processes should be complete...
Question 59: In which Knowledge Area is the project charter developed?...
Question 60: Which characteristic is unique to project work and does not ...
Question 61: The best approach to resolve the settlement of all outstandi...
Question 62: Assume you had a phase gate meeting with your Governance Boa...
Question 63: The Plan Stakeholder Management process belongs to which Pro...
Question 64: Your project has an EV of 100 work-days, an AC of 120 work-d...
Question 65: Which of the following characteristics are found in a functi...
Question 66: One of the objectives of a quality audit is to:...
Question 67: Long-term contracting is an important aspect of project qual...
Question 68: Which of the following is an input into the Develop Project ...
Question 69: Progressively elaborating high-level information into detail...
Question 70: Based on the following metrics: EV=$20,000, AC=$22,000, and ...
Question 71: Updates to organizational process assets such as procurement...
Question 72: When does Monitor and Control Risks occur?...
Question 73: Which of the following is a measure of the value of work com...
Question 74: Recognizing operations management is different than project ...
Question 75: Which is an input to the Verify Scope process?...
Question 76: Project management processes describe project work, while pr...
Question 77: You are beginning a new project staffed with a virtual team ...
Question 78: Which change request is an intentional activity that realign...
Question 79: The component of the human resource management plan that inc...
Question 80: Which process involves documenting the actions necessary to ...
Question 81: Which of the following is a tool and technique for activity ...
Question 82: Which of the following is an input to the Qualitative Risk A...
Question 83: You are managing a project that has five subcontractors. You...
Question 84: A team-building approach that facilitates concurrent enginee...
Question 85: The project team members have gotten together at the end of ...
Question 86: Processes in the Planning Process Group are typically carrie...
Question 87: Calculate the variance for the following: Pessimistic=50, Op...
Question 88: You are managing a project and the sponsor has removed the p...
Question 89: As project manager, you need a relatively fast and informal ...
Question 90: If operations on a work package were estimated to cost $1,50...
Question 91: Which is the document that presents a hierarchical project o...
Question 92: It often is advantageous to appoint a termination manager in...
Question 93: As part of a mid-project evaluation, the project sponsor has...
Question 94: The application of knowledge, skills, tools, and techniques ...
Question 95: There are a number of different earned value management rule...
Question 96: The project scope statement should be used in the identify r...
Question 97: When a backward pass is calculated from a schedule constrain...
Question 98: The principal function of a warranty is to______________...
Question 99: The cumulative CPI has been shown to be relatively stable af...
Question 100: The company is implementing a new project management approac...
Question 101: Which Knowledge Areas include processes from the Closing Pro...
Question 102: Who selects the appropriate processes for a project?...
Question 103: The nature of project work is such that it inevitably causes...
Question 104: The output that defines an approach to increase the support ...
Question 105: What is the term assigned to products or services having the...
Question 106: Which of the following terms indicates a deliverable-oriente...
Question 107: A stakeholder expresses a need not known to the project mana...
Question 108: What are seven consecutive data points on either side of the...
Question 109: Which of the following tools and techniques are utilized in ...
Question 110: What is the total float of the critical path?...
Question 111: Which of the following is an output of the Define Activities...
Question 112: To account for uncertainty in a schedule, reserve analysis m...
Question 113: A watch list of low priority risks is documented in the_____...
Question 114: Quality and credibility of the qualitative risk analysis pro...
Question 115: You are responsible for a project management training curric...
Question 116: The Define Scope process is in which of the following Proces...
Question 117: A risk response strategy that can be used for both threats a...
Question 118: In quality management, the practice "rework" is_____________...
Question 119: Which quality control technique illustrates the 80/20 princi...
Question 120: The performance measurement baseline consists of all the fol...
Question 121: Identify Stakeholders is the process of identifying all of t...
Question 122: The Project Manager is reviewing testing output. Generally, ...
Question 123: In project management, a temporary project can be:...
Question 124: What are the components of the "triple constraint"?...
Question 125: Which document in the project management plan can be updated...
Question 126: Which of the following is an input to the Direct and Manage ...
Question 127: Your organization is characterized by hierarchical organizat...
Question 128: An output of the Create WBS process is:...
Question 129: In which process might you use risk reassessment as a tool a...
Question 130: Job satisfaction, challenging work, and sufficient financial...
Question 131: Assigned risk ratings are based upon:...
Question 132: Assume that you are managing a project team. Your team is on...
Question 133: Which changes occur in risk and uncertainty as well as the c...
Question 134: Which type of graphic is displayed below? (Exhibit)...
Question 135: In the Plan Stakeholder Management process, expert judgment ...
Question 136: The Project Manager is creating an estimate for building a c...
Question 137: To practice effective schedule control, your project team mu...
Question 138: Which of the following is an example of push communication?...
Question 139: Which of the following is an input to Direct and Manage Proj...
Question 140: Which of the following is used to control schedule related i...
Question 141: An example of a group decision-ma king technique is:...
Question 142: During contract negotiations on large contracts, the negotia...
Question 143: You are implementing a project management methodology for yo...
Question 144: The Identify Stakeholders process is found in which Process ...
Question 145: Which of the following is a conflict resolution technique th...
Question 146: The cost baseline and project funding requirements are outpu...
Question 147: If you apply the configuration management system along with ...
Question 148: Fishbone diagrams are also known as what?...
Question 149: Which of the following events would result in a baseline upd...
Question 150: Which of the following are outputs of Develop Project Team?...
Question 151: Budgets reserved for unplanned changes to project scope and ...
Question 152: The business needs, assumptions, and constraints and the und...
Question 153: Which one of the following statements best characterizes an ...
Question 154: Which technique is utilized in the Control Schedule process?...
Question 155: Which item is an example of personnel assessment?...
Question 156: All the following statements are true about the grassroots e...
Question 157: Which items are an output of the Perform Integrated Change C...
Question 158: The basic approach to quality management in projects is to b...
Question 159: Which type of analysis is used to examine project results th...
Question 160: The process of identifying and documenting the specific acti...
Question 161: Which Control Stakeholder Engagement tool or technique allow...
Question 162: During which process does a project manager review all prior...
Question 163: What is the name of a graphic display of project team member...
Question 164: Which stakeholder communicates with higher levels of managem...
Question 165: Six sigma refers to the aim of setting tolerance limits at s...
Question 166: An effective technique for resolving conflict that incorpora...
Question 167: Labor, materials, equipment, and supplies are examples of:...
Question 168: An input to Develop Project Charter is a/an:...
Question 169: Using parametric estimating, if an assigned resource is capa...
Question 170: A primary function of a project management office is to supp...
Question 171: Which of the following is developed from the project scope b...
Question 172: In both the weak and strong matrix organizational structures...
Question 173: A workaround is______________
Question 174: When closing a project, it is a best practice to____________...
Question 175: The risk urgency assessment is a tool and technique used for...
Question 176: For complex procurement items, often contract negotiation ca...
Question 177: The procurement process that documents agreements and relate...
Question 178: The team has implemented a risk response plan when a vendor ...
Question 179: A project manager is appointed full-time to a project and is...
Question 180: Which input to the Manage Stakeholder Engagement process pro...
Question 181: The risk shared between the buyer and seller is determined b...
Question 182: Which of the following are three inputs to the risk register...
Question 183: Which input to the Manage Stakeholder Engagement process is ...
Question 184: The Project Manager and Functional Manager are having a disa...
Question 185: Activity cost estimates are quantitative assessments of the ...
Question 186: You are managing a project in which your team members all wo...
Question 187: A new manufacturing facility is being built for a consumer e...
Question 188: It is important on all projects to determine when and how hu...
Question 189: In organizing a project, a project manager must deal with co...
Question 190: Which process numerically analyzes the effect of identified ...
Question 191: Which Process Group typically consumes the bulk of a project...
Question 192: Which of the following is not a human resources process?...
Question 193: As you prepare your human resource plan, you need to determi...
Question 194: The customer has requested a five-week delay on the project ...
Question 195: The scope of a project cannot be defined without some basic ...
Question 196: Your project is using complex, unproven technology. Your tea...
Question 197: What can a responsibility assignment matrix (RAM) eliminate?...
Question 198: Consider a company that sells products to consumers: as one ...
Question 199: Change requests, project management plan updates, project do...
Question 200: Stakeholder communication requirements should be included as...
Question 201: Procurement documents are used in the identify stakeholder p...
Question 202: When cost variance is negative and schedule variance is posi...
Question 203: Which of the following is a tool or technique of the Define ...
Question 204: Which of the following statements correctly characterizes pu...
Question 205: Funding limit reconciliation is a tool and technique used in...
Question 206: In which process group is the scope first defined?...
Question 207: The project budget is set at $150,000. The project duration ...
Question 208: What are the Project Procurement Management processes?...
Question 209: Which process includes prioritizing risks for subsequent fur...
Question 210: A project manager who communicates to the project team thoug...
Question 211: The printing company is putting a policy in place to use jus...
Question 212: You are in the process of purchasing 67 desktop computers, m...
Question 213: As you are working on your telecommunications project, even ...
Question 214: The close project or phase process addresses actions and act...
Question 215: Which process involves the creation of a document that provi...
Question 216: As you manage the railroad switching station project, you ar...
Question 217: Alternatives generation often is useful in defining project ...
Question 218: Close procurements is a process that involves includes activ...
Question 219: As a result of the control stakeholder expectations process,...
Question 220: You are beginning a new project and a portion of the develop...
Question 221: A Pareto chart is a specific type of:...
Question 222: You are the Project Manager on a cellular bluetooth amplifie...
Question 223: Which type of organizational structure is displayed in the d...
Question 224: Change request status updates are an output of which process...
Question 225: In which Project Management Process Group is the project cha...
Question 226: You are planning a project and want to account for how the p...
Question 227: Prioritizing risks for further analysis or action by assessi...
Question 228: On large contracts, the contract administrator typically has...
Question 229: Inputs to Identifying Stakeholders include:...
Question 230: When a control chart is used to monitor performance of a pro...
Question 231: As the project manager, you have the option of proposing one...
Question 232: An example of an organizational process asset that could aff...
Question 233: Verification of project deliverables occurs during which pro...
Question 234: Which of the following is a tool or technique used in the Ac...
Question 235: The basis of identification for current or potential problem...
Question 236: Which of the following is a means of reaching a group decisi...
Question 237: The database project is approximately 85% complete. The proj...
Question 238: Deming's Fourteen Points provide a way for an organization t...
Question 239: You are working on a new project in your organization. You n...
Question 240: Which of the following schedule network analysis techniques ...
Question 241: What is the estimate at completion (EAC) if the budget at co...
Question 242: Which of the following is an example of contract administrat...
Question 243: A project will be using a vendor to purchase infrastructure ...
Question 244: All of the following are typically part of the project manag...
Question 245: Payment bonds are often required by the contract and require...
Question 246: You are remodeling your kitchen and decide to prepare a netw...
Question 247: The control chart is a tool used primarily to help__________...
Question 248: Which Develop Schedule tool and technique produces a theoret...
Question 249: The e-commerce project is six weeks behind schedule with fiv...
Question 250: Rather than use a WBS, your team developed a bill of materia...
Question 251: An element of the modern quality management approach used to...
Question 252: Work completed, key performance indicators, technical perfor...
Question 253: Recognizing the importance of preparing a stakeholder manage...
Question 254: When large or complex projects are separated into distinct p...
Question 255: Which tool or technique is used in Close Procurements?...
Question 256: Which of the following is an example of recommended correcti...
Question 257: Which process documents the business needs of a project and ...
Question 258: All the following are project baselines that are generally p...
Question 259: The Project Manager has some issues on the team between two ...
Question 260: Organizational theory is a tool used in which Project Human ...
Question 261: Which of the following strategies is used to deal with risks...
Question 262: Float on a Network diagram is also known as:...
Question 263: Which cost is associated with nonconformance?...
Question 264: Which tool or technique is required in order to determine th...
Question 265: The review of a sellers progress toward achieving the goals ...
Question 266: Table reporting, spreadsheet analysis, and presentations are...
Question 267: All the following are examples of project document updates f...
Question 268: Using the three-point estimating technique, if the most like...
Question 269: A change log for communications can be used to communicate t...
Question 270: A risk that arises as a direct result of implementing a risk...
Question 271: As you prepare to close out contracts on your project, you s...
Question 272: Requirements typically are classified into product requireme...
Question 273: How many Project Management Process Groups are there?...
Question 274: You are working on a project to upgrade the existing fiber-o...
Question 275: Which is an example of Administer Procurements?...
Question 276: What is the probability of occurrence if the risk rating is ...
Question 277: Which type of dependency is legally or contractually require...
Question 278: A project team attempts to produce a deliverable and finds t...
Question 279: A project has an EV of 100 workdays, an AC of 120 workdays, ...
Question 280: A risk response strategy in which the project team shifts th...
Question 281: The item that provides more detailed descriptions of the com...
Question 282: Diagram: (Exhibit) If the imposed finish time in question 3 ...
Question 283: As you use the critical chain method in lieu of the critical...
Question 284: In which of the following methods of resolving conflict will...
Question 285: When a seller breaches a contract, the buyer cannot receive_...
Question 286: The key benefit of the Monitoring and Controlling Process Gr...
Question 287: Funding limit reconciliation is a tool and technique of whic...
Question 288: You are using earned value progress reporting for your curre...
Question 289: You are using earned value progress reporting for your curre...
Question 290: If the most likely duration of an activity is five weeks, th...
Question 291: The Project Manager has weekly scheduled status meetings wit...
Question 292: Your project is proceeding according to schedule. You have j...
Question 293: Administer Procurements is part of which Process Group?...
Question 294: Decomposition, rolling wave planning, and templates are all ...
Question 295: Diagram: (Exhibit) What is the duration of the critical path...
Question 296: The purpose of economic value added (EVA) is to_____________...
Question 297: When managing projects, one important technique is capturing...
Question 298: The cumulative cost curve for planned and actual expenditure...
Question 299: Which index is the calculated projection of cost performance...
Question 300: Who determines which dependencies are mandatory during the S...
Question 301: You are project manager on a systems engineering project des...
Question 302: A projects purpose or justification, measurable project obje...
Question 303: Ensuring that projects and programs are reviewed to prioriti...
Question 304: A project can be defined as a:
Question 305: Which process involves aggregating the estimated costs of th...
Question 306: In the Plan Procurement Management process, which source sel...
Question 307: In an organization with a projectized organizational structu...
Question 308: Sample attributes of a communications management plan includ...
Question 309: Monte Carlo is which type of risk analysis technique?...
Question 310: How is the schedule variance calculated using the earned val...
Question 311: The ISO 9000 standards provide______________...
Question 312: Which type of estimating is used to improve the accuracy of ...
Question 313: One output of the control costs process is cost forecasts, w...
Question 314: The project planning is progressing on budget. The Project M...
Question 315: You are in the initial phase of a project and are doing an e...
Question 316: Which tool within the Perform Quality Control process identi...
Question 317: You plan to hold a series of meeting as you execute the proj...
Question 318: Objectives for conducting performance appraisals during the ...
Question 319: In which process is a project manager identified and given t...
Question 320: Organizational process assets, a lessons-learned database, a...
Question 321: Because you are working under a firm-fixed-price contract, m...
Question 322: An output of Control Schedule is:...
Question 323: The process for performing variance analysis may vary, depen...
Question 324: Because your project is slated to last five years, you belie...
Question 325: Diagram: (Exhibit) What is the float for Activity G?...
Question 326: Which one of the following is a key input to the define acti...
Question 327: Which of the following tools and techniques is used in the c...
Question 328: The reason that the cost performance index (CPI) is shown as...
Question 329: Which of the following is a tool and technique for Estimate ...
Question 330: Crosswind Custom Homes is building a customer's dream house....
Question 331: On your project you want to avoid bureaucracy, so you adopt ...
Question 332: A weighting system can be used for all but which one of the ...
Question 333: Conditions that are not under the control of the project tea...
Question 334: A retail expansion project is going relatively well, but the...
Question 335: The Closing Process Group includes which of the following Kn...
Question 336: A Project Manager has completed the Scope Planning process. ...
Question 337: If you decide to follow an open subordination approach to re...
Question 338: Different types of project phases are used on projects, and ...
Question 339: The approaches, tools, and data sources that will be used to...
Question 340: Assume your company is a leader in the market in production ...
Question 341: The project is using a new server that cost $25,000 US. The ...
Question 342: According to Herzberg's Motivator-Hygiene Theory, when achie...
Question 343: Cost aggregation is typically performed by aggregating work ...
Question 344: Scope verification is PRIMARILY concerned with which of the ...
Question 345: Which of the following is an input to Develop Human Resource...
Question 346: Risk categorization is a tool or technique used in which pro...
Question 347: Which conflict resolution technique searches for solutions t...
Question 348: Which technique is commonly used for the Quantitative Risk A...
Question 349: The information technology system for the national power gri...
Question 350: Projects are supposed to succeed, not fail. However, termina...
Question 351: What is the definition of Direct and Manage Project Executio...
Question 352: Projects are undertaken by an organization to support the:...
Question 353: Which of the following is not an example of team development...
Question 354: Activity A has a pessimistic (P) estimate of 36 days, a most...
Question 355: The major difference between the project coordinator and pro...
Question 356: The milestone list is an input to which process from the Pla...
Question 357: Which of the following involves making information available...
Question 358: The Project Manager and team are planning the project. They ...
Question 359: The technique of subdividing project deliverables into small...
Question 360: Plan Risk Management is the process of defining how to:...
Question 361: Project A has a NPV of $275K US over 2.5 years. Project B ha...
Question 362: Thinking back to lessons that your company learned from expe...
Question 363: Which input to the Plan Risk Management process provides inf...
Question 364: The consulting company has created the scope of work for the...
Question 365: A number of items in the stakeholder management plan are sim...
Question 366: Successful project management involves both project leadersh...
Question 367: The team is involved in defining what is needed to ensure pr...
Question 368: Rank ordering of defects should be used to guide corrective ...
Question 369: You are the project manager for the construction of an incin...
Question 370: You are planning to conduct the team-building portion of you...
Question 371: You must consider direct costs, indirect costs, overhead cos...
Question 372: One way to help mitigate personnel risks that may occur duri...
Question 373: What is the lowest level in the Work Breakdown Structure cal...
Question 374: Although the project charter serves to state the project man...
Question 375: The "rule of seven" as applied to statistical process contro...
Question 376: When does risk monitoring and control occur?...
Question 377: Which term describes contract costs that are traceable to or...
Question 378: Stakeholder engagement must be controlled on a continuous ba...
Question 379: Overall cost estimates must be allocated to individual activ...
Question 380: The project will be using a company to provide the technicia...
Question 381: The processes required to establish the scope of the project...
Question 382: Portfolio Management is management of:...
Question 383: All projects involve some extent of change, because they inv...
Question 384: You are working on a project and want to know how many activ...
Question 385: The key management skills required during the adjourning sta...
Question 386: Control charts, flowcharting, histograms, Pareto charts, and...
Question 387: A number of different decision-making styles can be used in ...
Question 388: If the probability of event 1 is 80 percent and of event 2 i...
Question 389: Which process determines the risks that may affect the proje...
Question 390: Which tool or technique allows a large number of ideas to be...
Question 391: The three types of estimates that PERT uses to define an app...
Question 392: You have been a project manager for seven years. You now are...
Question 393: You are the Project Manager on a merger and acquisition proj...
Question 394: Which term is NOT a common name for a procurement document t...
Question 395: A tool and technique used in the Develop Project Charter pro...
Question 396: At the end of the project, what will be the value of SV?...
Question 397: As project manager, you have assembled the team to prepare a...
Question 398: What is the main output of Monitoring and Controlling?...
Question 399: Status of deliverables, implementation status for change req...
Question 400: The most commonly used type of precedence relationship in th...
Question 401: What is the risk rating if the probability of occurrence is ...
Question 402: An input to the Plan Stakeholder Management process is:...
Question 403: As head of the PMO, you will receive performance reports for...
Question 404: Which grid shows which resources are tied to work packages?...
Question 405: One purpose of the communications management plan is to prov...
Question 406: You were assigned recently as the project manager of a progr...
Question 407: The project manager at an organization has just realized tha...
Question 408: Which characteristics do effective project managers possess?...
Question 409: The key inputs to the validate scope process include all the...
Question 410: In the basic communication model, which term refers to the m...
Question 411: Project A is being administered using a matrix form of organ...
Question 412: Which tool and technique of quality planning involves compar...
Question 413: At which stage of the project should certain factors such as...
Question 414: Which type of analysis is used to develop the communications...
Question 415: You are fairly new to managing a project but have been a tea...
Question 416: Which type of managers do composite organizations involve?...
Question 417: Which type of chart is a graphic representation of a process...
Question 418: Which input will be used when tasked with developing the hum...
Question 419: Which of the following is an output of the Monitor and Contr...
Question 420: Which key interpersonal skill of a project manager is define...
Question 421: Which process involves determining, documenting, and managin...
Question 422: Assume you are working on a multi-phase project as your proj...
Question 423: An output of the Validate Scope process is:...
Question 424: Stakeholder satisfaction should be managed as a key project:...
Question 425: The team is involved in defining what is needed to ensure th...
Question 426: The individual or group that provides resources and support ...
Question 427: Projects are separated into phases or subprojects; these pha...
Question 428: Outputs of the Control Communications process include:...
Question 429: Create WBS is part of which of the following Knowledge Areas...
Question 430: Which type of agreement is legal, contractual, and between t...
Question 431: Sensitivity analysis is typically displayed as a/an:...
Question 432: A final project report is a recommended best practice. Altho...
Question 433: Which of the following is an output of the Information Distr...
Question 434: Updates of organizational process assets that are an output ...
Question 435: Having prepared stakeholder management plans on previous pro...
Question 436: Conflicts in which following three areas represent the major...
Question 437: Constant bickering, absenteeism, and substandard performance...
Question 438: Success is measured by benefits realization for a:...
Question 439: A regression line is used to estimate:...
Question 440: Information collected on the status of project activities be...
Question 441: When a project is undertaken to reduce defects in a product ...
Question 442: The project manager for XYZ stationers is sequencing the act...
Question 443: Configuration identification, configuration status accountin...
Question 444: The last step in the stakeholder analysis process is to_____...
Question 445: What type of planning is used where the work to be accomplis...
Question 446: The following is a network diagram for a project. (Exhibit) ...
Question 447: An input to the Identify Risks process is the:...
Question 448: Which of the following is an input to Control Scope?...
Question 449: If you want to calculate the ETC based on your expectations ...
Question 450: The completion of the project scope is measured against the:...
Question 451: Assume that your project in the food service industry involv...
Question 452: An output of the Develop Project Team process is:...
Question 453: Work performance information is an output of which process?...
Question 454: The primary result of effective team development is_________...
Question 455: Your company is in the project management training business....
Question 456: The CPI is .92, and the EV is US$172,500.What is the actual ...
Question 457: Which of the following includes how requirements activities ...
Question 458: Which quality tool incorporates the upper and lower specific...
Question 459: Which Collect Requirements output links the product requirem...
Question 460: You are conducting a stakeholder analysis on your project. A...
Question 461: What is a technique used in the performance reporting proces...
Question 462: Which action should a project manager take to ensure that th...
Question 463: What happens to a stakeholder's project influence over time?...
Question 464: Which type of analysis is used to determine the cause and de...
Question 465: Under which type of contract does the seller receive reimbur...
Question 466: What are the key components of the communication model?...
Question 467: Which cost estimate technique includes contingencies to acco...
Question 468: Which of the following is an example of a risk symptom?...
Question 469: A project you have been managing is falling behind schedule....
Question 470: Buyers use a variety of methods to provide incentives to a s...
Question 471: What type of project structure is a hierarchically organized...
Question 472: Change control procedures, configuration management knowledg...
Question 473: It is critical during the proposal preparation stage that___...
Question 474: Which of the following is not a regulation?...
Question 475: The CPI on your project is 0.84. This means that you should_...
Question 476: Within a matrix organization, dual reporting of team members...
Question 477: On a wireless internet access project, the team is large wit...
Question 478: You have decided to organize a study group of other project ...
Question 479: What are the formal and informal policies, procedures, and g...
Question 480: When painting a bedroom, preparing the walls can be done whi...
Question 481: You are project manager for a systems integration effort and...
Question 482: You are assigned to implement the project control plan. What...
Question 483: Which tool or technique of the Define Activities process all...
Question 484: An input of the Create WBS process is:...
Question 485: You are a personnel management specialist recently assigned ...
Question 486: Forecasts, requested changes, recommended corrective actions...
Question 487: A project team member agrees to change a project deliverable...
Question 488: During which process would stakeholders provide formal accep...
Question 489: Which items are components of a project management plan?...
Question 490: The key to effective cost control is______________...
Question 491: You are working on a construction project in a city differen...
Question 492: You are working on a project that management has decided to ...
Question 493: As a Project Manager you are managing a project that has man...
Question 494: In scope control it is important to determine the cause of a...
Question 495: Which tool and technique identifies inefficient and ineffect...
Question 496: Which Perform Quality Control tool graphically represents ho...
Question 497: Changes to formally controlled documentation, plans, etc. to...
Question 498: The Monitoring and Controlling Process Group includes proces...
Question 499: Change requests are an output from which Project Integration...
Question 500: During which process group is the quality policy determined?...
Question 501: Which type of analysis systemically gathers and analyzes qua...
Question 502: The methodology that combines scope, schedule, and resource ...
Question 503: Which of the following Process Groups covers all Project Man...
Question 504: Which process uses occurrence probability and impact on proj...
Question 505: Analogous cost estimating relies on which of the following t...
Question 506: Which Process Group contains those processes performed to de...
Question 507: The project governance approach should be described in the:...
Question 508: You have decided to award a contract to a seller that has pr...
Question 509: During your project, you will have a number of different typ...
Question 510: Which tool or technique of Plan Quality involves comparing a...
Question 511: A project management office manages a number of aspects incl...
Question 512: Team building should be ongoing throughout the project life ...
Question 513: Which of the following factors contributes the most to team ...
Question 514: What is one of the objectives of Project Risk Management?...
Question 515: Which category of contracts are sellers legally obligated to...
Question 516: The scope management plan and scope baseline are contained i...
Question 517: To which process is work performance information an input?...
Question 518: Often in working as a project manager, it is easy to overloo...
Question 519: Working in the systems integration field, you are primarily ...
Question 520: Quality inspections also may be called______________...
Question 521: Activity A is worth $400, is 95% complete, and actually cost...
Question 522: The Create WBS process is in which of the following Project ...
Question 523: Your quality assurance department recently performed a quali...
Question 524: Which of the following is a narrative description of product...
Question 525: You learn that a former boss of yours who is a PMP has commi...
Question 526: As project manager, you are primarily responsible for implem...
Question 527: A supporting input for controlling stakeholder engagement is...
Question 528: Having worked previously on projects as a team member, you a...
Question 529: The definition of operations is a/an:...
Question 530: Activity A is worth $200, is 100% complete, and actually cos...
Question 531: Which of the following consists of the detailed project scop...
Question 532: A technique used to determine the cause and degree of differ...
Question 533: Requirements documentation will typically contain at least:...
Question 534: What does a CPI value greater than 1.0 indicate?...
Question 535: Which of the following is the primary output of the Identify...
Question 536: The company has been plagued by disorganized projects that a...
Question 537: What is the schedule performance index (SPI) if the planned ...
Question 538: The ways in which the roles and responsibilities, reporting ...
Question 539: Project managers who lead by example and follow through on t...
Question 540: Variance and trend analysis is a tool and technique used in ...
Question 541: A key tool and technique used in define scope is____________...
Question 542: Based on a recent quality audit of your project, your organi...
Question 543: Research has shown that during the execution phase of the pr...
Question 544: Effective communication occurs in groups as well as between ...
Question 545: Which stakeholder approves a project's result?...
Question 546: Project managers for international projects should recognize...
Question 547: Which item is a formal proposal to modify any document, deli...
Question 548: The product scope description is used to:...
Question 549: While working as the project manager on a new project to imp...
Question 550: The project management team has performed earned value analy...
Question 551: As the project progresses, which of the following is routine...
Question 552: The following is a network diagram for a project. (Exhibit) ...
Question 553: Which of the following is an output of the Conduct Procureme...
Question 554: On your project, scope changes, constraints, assumptions, in...
Question 555: You are working on a new project in your city to construct a...
Question 556: Which knowledge area employs the processes required to ensur...
Question 557: Which written document helps monitor who is responsible for ...
Question 558: One of the fundamental tenets of modern quality management s...
Question 559: The total of the planned value (PV) is also known as:...
Question 560: Payback period, return on investment, internal rate of retur...
Question 561: Which of the following is TRUE about most project life cycle...
Question 562: Which process involves monitoring the status of the project ...
Question 563: Calculate the standard deviation for the following: Pessimis...
Question 564: Which of the following are outputs of the Monitor and Contro...
Question 565: Decomposition is a technique used for both WBS development a...
Question 566: What is a deliverable-oriented, hierarchical decomposition o...
Question 567: Which quality tool may prove useful in understanding and est...
Question 568: Which of the following is an information gathering technique...
Question 569: The Human Resource Management processes are:...
Question 570: Which is used to solicit proposals from prospective sellers?...
Question 571: The Project Management Process Group in which performance is...
Question 572: Because risk management is relatively new on projects in you...
Question 573: The project manager needs to review the templates in use. Th...
Question 574: A key member of your project has deep technical skills and m...
Question 575: You are finalizing all the contracts and ensuring that they ...
Question 576: What is the responsibility of the project manager and the fu...
Question 577: Which schedule method allows the project team to place buffe...
Question 578: A purchase order is a good example of which form of contract...
Question 579: What is the difference between the critical path and the cri...
Question 580: You are working on a project with 15 stakeholders. The numbe...
Question 581: Statistical sampling is a method in perform quality control ...
Question 582: Which Process Group's purpose is to track, review, and regul...
Question 583: The probability and impact matrix is primarily used to:...
Question 584: Which is an input to the Scope Verification Process?...
Question 585: For a project to be successful, the project team must do whi...
Question 586: Soft logic is also known as what type of dependency?...
Question 587: The CPI is .92, and the EV is US$172,500. What is the actual...
Question 588: Ensuring that both parties meet contractual obligations and ...
Question 589: The iterative process of increasing the level of detail in a...
Question 590: You are establishing a PMO that will have a project manageme...
Question 591: Which one of the following represents a constraint on the ac...
Question 592: Which enterprise environmental factors are considered during...
Question 593: Which process is responsible for monitoring the status of th...
Question 594: A contract management plan is a subsidiary of what other typ...
Question 595: The diagram below is an example of a: (Exhibit)...
Question 596: What component of the project scope definition defines proje...
Question 597: Information distribution involves making needed information ...
Question 598: To please the customer, a project team member delivers a req...
Question 599: Recently, your company introduced a new processing system fo...
Question 600: If a team member, when facing schedule delays and cost overr...
Question 601: The process to ensure that appropriate quality standards and...
Question 602: The retail chain will be using a vendor to provide engineers...
Question 603: A number of factors affect make-or-buy decisions such as____...
Question 604: Activity resource requirements and the resource breakdown st...
Question 605: The process of conferring with others to come to terms or re...
Question 606: Which Process Group includes the Manage Stakeholder Engageme...
Question 607: Assigning more talented resources to the project to reduce t...
Question 608: Cost baseline is an output of which of the following process...
Question 609: The undistributed budget is part of the______________...
Question 610: A benefit of using virtual teams in the Acquire Project Team...
Question 611: On what is project baseline development established?...
Question 612: What is the number of stakeholders, if the project has 28 po...
Question 613: While preparing the project management plan on a weekly basi...
Question 614: You are leading a team to recommend an equitable reward and ...
Question 615: Inputs to the Define Activities process include:...
Question 616: When writing payment terms in your fixed-price subcontracts ...
Question 617: The cost benefit analysis tool is used for creating:...
Question 618: How is scheduled variance calculated using the earned value ...
Question 619: Which Project Time Management process includes bottom-up est...
Question 620: Which of the following Project Communication Management proc...
Question 621: A Project Manager has been working on quality process of a p...
Question 622: Approved change requests, approved corrective actions, and u...
Question 623: You can use various estimating approaches to determine activ...
Question 624: What type of reward can hurt team cohesiveness?...
Question 625: The following is a network diagram for a project. (Exhibit) ...
Question 626: Although your company's project life cycle does not mandate ...
Question 627: Which schedule compression technique has phases or activitie...
Question 628: An imposed date for completion of the project by the custome...
Question 629: Which process involves identifying and documenting the logic...
Question 630: The project planning is progressing on schedule. The Project...
Question 631: The Process Group that involves coordinating people and reso...
Question 632: As head of the project management office, you need to focus ...
Question 633: Which of the following are placed at selected points in the ...
Question 634: There has been a great delay in waiting to get the charter a...
Question 635: The component of the risk management plan that documents how...
Question 636: During which process would you obtain stakeholders' formal a...
Question 637: Work performance information and cost forecasts are outputs ...
Question 638: The buyer has negotiated a cost-plus-incentive fee contract ...
Question 639: The project has gone smoothly so far. The team members appea...
Question 640: Which standard examines an enterprise's project management p...
Question 641: Which of the following calculations CANNOT be used to determ...
Question 642: Which of the following is an input to the Perform Qualitativ...
Question 643: Which of the following is the best description of configurat...
Question 644: The project manager notes that stakeholders are aware of the...
Question 645: The Project Human Resource Management process that involves ...
Question 646: Managing five contractors on your project for a new stadium ...
Question 647: The process of formalizing acceptance of the completed proje...
Question 648: Which process in Project Time Management includes reserve an...
Question 649: Activity A is worth $300, is 100% complete, and actually cos...
Question 650: A no-cost settlement sometimes is used______________...
Question 651: Which of the following procurement processes results in the ...
Question 652: Your project has a budget of $1.5 million for the first year...
Question 653: You want to minimize the impact of changes on your project, ...
Question 654: Ideally, a project manager should be selected and assigned a...
Question 655: An input to Close Project or Phase is:...
Question 656: You are managing a new technology project designed to improv...
Question 657: You are a project manager leading the construction project o...
Question 658: Another name for an Ishikawa diagram is:...
Question 659: The lowest level normally depicted in a work breakdown struc...
Question 660: When alternative dispute resolution (ADR) is necessary, whic...
Question 661: Because communications planning often is linked tightly with...
Question 662: Which of the following would a Contract Administrator use if...
Question 663: During the stages of team development, your team is in which...
Question 664: The terms strong matrix, balanced matrix, and weak matrix wh...
Question 665: On your systems development project, you noted during a revi...
Question 666: Which term describes the failure by either the buyer or the ...
Question 667: Which of the following inputs is required for the WBS creati...
Question 668: Projects are authorized by which of the following individual...
Question 669: The issue log is useful in control communications because it...
Question 670: Which of the following is an output of the Perform Integrate...
Question 671: A Project Management Office (PMO) manages a number of aspect...
Question 672: Marketplace conditions are an input to which one of the foll...
Question 673: While implementing an approved change, a critical defect was...
Question 674: The company is implementing a quality improvement standard o...
Question 675: You are a Project Manager at Dewey, Cheatum, and Howe and as...
Question 676: Which is the Define Scope technique used to generate differe...
Question 677: Project management processes ensure the:...
Question 678: Which Define Activities tool or technique is used for dividi...
Question 679: Testing falls into which of the following categories of cost...
Question 680: Which tool or technique is used to develop a project charter...
Question 681: The project is going through quality assurance. Which of the...
Question 682: Major difficulties arise when multiple projects need to be m...
Question 683: The team is testing the work of the project and is having is...
Question 684: One of the key benefits of the Plan Human Resource Managemen...
Question 685: The iterative and interactive nature of the Process Groups c...
Question 686: Which tool or technique is used in Manage Stakeholder Expect...
Question 687: The primary benefit of the Plan Schedule Management process ...
Question 688: An output of the Close Project (or Close Phase) process is:...
Question 689: A work package has been scheduled to cost $1,000 to complete...
Question 690: Inputs to the Plan Schedule Management process include:...
Question 691: In order for a matrix organizational approach to be successf...
Question 692: Your organization has decided to use project management for ...
Question 693: In the below path convergence example, if the odds of comple...
Question 694: All of the following are objectives of a quality audit______...
Question 695: An input to the Perform Quantitative Risk Analysis process i...
Question 696: A conflict resolution approach that is NOT considered to be ...
Question 697: As a Project Manager, your first priority is to accomplish t...
Question 698: The project scope statement addresses and documents all the ...
Question 699: Crosswind Custom Homes is building a customer's dream house....
Question 700: At which point of the project is the uncertainty the highest...
Question 701: Risk mitigation involves______________...
Question 702: Which type of risk diagram is useful for showing time orderi...
Question 703: Contested changes are requested changes when the buyer and s...
Question 704: As the buyer is involved in creating request for proposals (...
Question 705: Your cost control specialist has developed a budget plan for...
Question 706: Assume your stakeholder management plan has been approved. Y...
Question 707: Which of the following types of a dependency determination i...
Question 708: As you work on your project to update its software training ...
Question 709: The process of monitoring the status of the project and prod...
Question 710: Which tool is used to develop technical details within the p...
Question 711: You are managing a project with team members located at cust...
Question 712: What is the schedule performance index (SPI) using the follo...
Question 713: Project execution must be compared, and deviations must be m...
Question 714: Which process is conducted from project inception through co...
Question 715: Which of the following is a tool and technique used to monit...
Question 716: Which basic quality tool is most useful when gathering attri...
Question 717: On a large medical billing system project, the team is large...
Question 718: The e-commerce project has gone well other than the fact tha...
Question 719: The Perform Integrated Change Control process occurs in whic...
Question 720: Which of the following is a schedule network analysis techni...
Question 721: Which process involves aggregating the estimated costs of th...
Question 722: You have been assigned as the project manager for a major pr...
Question 723: You finally have been appointed project manager for a major ...
Question 724: Analytical techniques are a tool and technique of which proc...
Question 725: The project has a current cost performance index of 0.80. As...
Question 726: A project manager providing information to the right audienc...
Question 727: The project is nearing completion. The team is involved in a...
Question 728: Cost of quality (COQ) refers to total cost of/to:...
Question 729: Which of the following methods is a project selection techni...
Question 730: The process improvement plan details the steps for analyzing...
Question 731: Schedule milestones and a predefined budget are examples of:...
Question 732: Which of the following best relates to unknown unknowns?...
Question 733: The sponsor plays a key role in project success. Which of th...
Question 734: When you review cost performance data on your project, diffe...
Question 735: Based on the following metrics: EV= $20,000, AC= $22,000, an...
Question 736: Power, urgency, and legitimacy are attributes of which stake...
Question 737: Which of the following change requests can bring expected fu...
Question 738: Modifications may be needed to the WBS and WBS dictionary be...
Question 739: The project charter is an input to which process?...
Question 740: Crosswind Custom Homes is building a customer's dream house....
Question 741: The degree, amount, or volume of risk that an organization o...
Question 742: A project requires a component with well-understood specific...
Question 743: Reserve analysis is a tool and technique used in which proce...
Question 744: Your firm specializes in roller-coaster construction. It rec...
Question 745: An output of the Plan Quality Management process is:...
Question 746: In project communications, the first step in a written commu...
Question 747: The process of obtaining seller responses, selecting a selle...
Question 748: Which of the following is a key input to define activities?...
Question 749: An input to the Collect Requirements process is the:...
Question 750: The chances for successful completion of a multidisciplinary...
Question 751: During a bidders conference, it is important that___________...
Question 752: Resource calendars are included in the:...
Question 753: Which statement correctly describes the value of a business ...
Question 754: Improvement to the processes and the product is a goal of pr...
Question 755: The Project Manager is involved in acquiring the project tea...
Question 756: Which of the following investigates the likelihood that each...
Question 757: Today, the primary cause of why projects are not completed o...
Question 758: Which of the following is a tool or technique for the Plan P...
Question 759: Which of the following formulas calculates the number of com...
Question 760: A tool and technique used during the Define Scope process is...
Question 761: Statements of organizational policies and philosophies, posi...
Question 762: The person assigned by the performing organization to be res...
Question 763: The project is very challenging and has been very trying on ...
Question 764: What is a tool to improve team performance?...
Question 765: The end point of a project phase can be referred to as:...
Question 766: Organizational planning impacts projects by means of project...
Question 767: Which tool or technique used in the Control Procurements pro...
Question 768: Collecting requirements is critical in project scope managem...
Question 769: To which process is work performance information an input?...
Question 770: A disadvantage associated with virtual teams is that they:...
Question 771: Which document describes the necessary information to determ...
Question 772: Project managers should pay attention to critical and subcri...
Question 773: Who provides the inputs for the original estimates of activi...
Question 774: Which technique is utilized in the Schedule Control process?...
Question 775: The team is in the process of validating that the quality pl...
Question 776: A project manager requesting industry groups and consultants...
Question 777: Activity cost estimates and the project schedule are inputs ...
Question 778: The degree of uncertainty an entity is willing to take on in...
Question 779: Which document defines how a project is executed, monitored ...
Question 780: Assume you have identified your stakeholders and are prepari...
Question 781: In some cases, contract termination refers to______________...
Question 782: Correlated and contextualized information on how closely the...
Question 783: Your project has been under way for some time, but indicator...
Question 784: Which organizational process assets update is performed duri...
Question 785: Ranking risks is performed in which of the following?...
Question 786: The greatest degree of uncertainty is encountered during whi...
Question 787: A purchase order for a specified item to be delivered by a s...
Question 788: A Project Manager is assigned to a project that is in the co...
Question 789: Two key inputs to the perform quantitative risk analysis pro...
Question 790: Your project manager has requested that you provide him with...
Question 791: A number of items may be part of the schedule data for the p...
Question 792: The IT initiative project is on schedule and under budget. T...
Question 793: You work as a project manager in the largest hospital in the...
Question 794: Diagram: (Exhibit) If a project planner imposes a finish tim...
Question 795: You are the Project Manager for a national satellite rollout...
Question 796: In the Initiating Process Group, at what point does the proj...
Question 797: The WBS represents all product and project work, including p...
Question 798: You are a member of a project selection committee that uses ...
Question 799: Within project integration management, the statement of work...
Question 800: The purpose of using what-if analysis in schedule control is...
Question 801: Which of the following is an input to Direct and Manage Proj...
Question 802: As you prepare to close your project, which of the following...
Question 803: Which of the following is a group decision-making technique?...
Question 804: In which type of contract are the performance targets establ...
Question 805: Two people at work are discussing roles and responsibilities...
Question 806: Inputs to the Plan Risk Management process include the:...
Question 807: The project is progressing well but has begun to experience ...
Question 808: A number of approaches can be helpful when estimating resour...
Question 809: Lessons learned are created and project resources are releas...
Question 810: Which of the following choices is a contract closure tool or...
Question 811: Risk responses reflect an organization's perceived balance b...
Question 812: The Process Group in which the internal and external stakeho...
Question 813: The following chart contains information about the tasks in ...
Question 814: In a construction project schedule, what is the logical rela...
Question 815: Identifying interrelationships and potential overlap between...
Question 816: The baseline for evaluating whether requests for changes or ...
Question 817: The reason that the schedule performance index (SPI) is show...
Question 818: What is a hierarchically organized depiction of the identifi...
Question 819: Which of the following is an example of the simplest fixed-p...
Question 820: As of the fourth month on the Acme project, cumulative plann...
Question 821: PMBOI Guide is a standard that describes:...
Question 822: Your role in the project includes helping to resolve problem...
Question 823: A Project Manager has been working on quality process of a p...
Question 824: All the following are outputs of the estimate cost process E...
Question 825: Technical capability, past performance, and intellectual pro...
Question 826: Which of the following response strategies are appropriate f...
Question 827: The process of identifying and documenting relationships amo...
Question 828: Which of the following correctly describes when organization...
Question 829: What is the typical role of senior management on a project?...
Question 830: The project team should have a working knowledge of statisti...
Question 831: The scope management plan and scope baseline are contained i...
Question 832: Which process develops options and actions to enhance opport...
Question 833: The following chart contains information about the tasks in ...
Question 834: The risk register may need to be updated as an output of whi...
Question 835: A number of organizational process assets are useful as inpu...
Question 836: Functional managers play a vital role in ensuring project su...
Question 837: Which of the following buffers protects the target finish da...
Question 838: Most statistical simulations of budgets, schedules, and reso...
Question 839: Co-location is a tool and technique of:...
Question 840: Which element does a project charter contain?...
Question 841: Which risk response strategy is common for both positive and...
Question 842: Your approved project schedule was based on resource levelin...
Question 843: Types of internal failure costs include:...
Question 844: Which of the following is an output of Direct and Manage Pro...
Question 845: The scope management plan is a subsidiary of which project d...
Question 846: Which of the following is an output of Define Scope?...
Question 847: Projects that share common outcomes, collective capability, ...
Question 848: The process of identifying and documenting project roles, re...
Question 849: Which type of manager is assigned by the performing organiza...
Question 850: As project manager, you plan to conduct a "kickoff" meeting ...
Question 851: Perform Quality Control is accomplished by:...
Question 852: In defining a milestone, which of the following is correct?...
Question 853: Which tool or technique is used in the Plan Scope Management...
Question 854: Which stakeholder classification model groups stakeholders b...
Question 855: Which of the following risk response strategies involves all...
Question 856: Which of the following statements is true regarding project ...
Question 857: To meet regulatory requirements, you need to crash your proj...
Question 858: The pilot for PM Airlines is in the process of flying from D...
Question 859: Which type of project management office (PMO) supplies templ...
Question 860: The estimate costs process uses all the following tools and ...
Question 861: Which of the following is an input of the Define Activities ...
Question 862: In project development, schedule information such as who wil...
Question 863: Project quality management was once thought to include only ...
Question 864: Tools and techniques used to perform quality assurance inclu...
Question 865: Plan-do-check-act is also known as:...
Question 866: Impacts to other organizational areas, levels of service, an...
Question 867: Which of the following would a team create as a result of us...
Question 868: When you are about to terminate a contract, the one place to...
Question 869: You are leading a team to review and improve the project sel...
Question 870: The organization's perceived balance between risk taking and...
Question 871: The project is in a projectized environment. There are signi...
Question 872: Which illustrates the connection between work that needs to ...
Question 873: Assume you are managing a project, and your project manageme...
Question 874: Oftentimes when a project is terminated, senior managers wil...
Question 875: You have a number of costs to track and manage because your ...
Question 876: An input to the Perform Integrated Change Control process is...
Question 877: You are the Project Manager for a high speed data communicat...
Question 878: An input to the Create WBS process is a:...
Question 879: Validate scope works hand-in-hand with control quality and g...
Question 880: Although your project team is working virtually, you are str...
Question 881: You are working on a contract in a remote location. The cont...
Question 882: Which is an enterprise environmental factor?...
Question 883: On the electric company project the government implemented a...
Question 884: Expert judgment is a best practice as a tool and technique i...
Question 885: The following chart contains information about the tasks in ...
Question 886: In defining a risk trigger, which of the following is most a...
Question 887: The plan quality management process includes all the followi...
Question 888: Which process group contains the processes performed to fina...
Question 889: A tool and technique used during the Create WBS process is:...
Question 890: During what process is the quality policy determined?...
Question 891: An input to the Plan Procurement Management process is:...
Question 892: A strengths, weaknesses, opportunities, and threats (SWOT) a...
Question 893: You are a Project Manager managing the building of a housing...
Question 894: Which Define Activities output extends the description of th...
Question 895: Activities on the critical path have which type of float?...
Question 896: Managing ongoing production of goods and services to ensure ...
Question 897: The project team is developing rules for reporting status on...
Question 898: Which estimating technique uses the actual costs of previous...
Question 899: You are conducting a stakeholder analysis on your project. Y...
Question 900: Which technique is commonly used for the Perform Quantitativ...
Question 901: The direct and manage project work process truly is importan...
Question 902: Project deliverables are the outputs that include the produc...
Question 903: Stakeholders often have issues, and you have asked each of y...
Question 904: Assume that you were the first person in your company to be ...
Question 905: Validate scope______________
Question 906: A car company authorized a project to build more fuel-effici...
Question 907: In the Estimate Activity Durations process, productivity met...
Question 908: The Project Manager is creating an estimate for building a c...
Question 909: Which of the following are examples of interactive communica...
Question 910: Which of the following types of contracts has the least risk...
Question 911: You work for a software development company that has followe...
Question 912: The project scope statement and resource calendars are input...
Question 913: There are three uses and types of Pareto analysis. If you wi...
Question 914: Having worked previously as a software project manager, you ...
Question 915: Which of the following is a complete set of indexed contract...
Question 916: The project management processes presented in the PMBOK Guid...
Question 917: Which of the following is a schematic display of the project...
Question 918: Which of the following makes changes to formally control doc...
Question 919: Project Management Process Groups are linked by:...
Question 920: Which Project Management Process Group includes Collect Requ...
Question 921: A project manager should document the escalation path for un...
Question 922: The highest risk impact generally occurs during which one of...
Question 923: You are the project manager for a major logistics installati...
Question 924: The team you have organized for your new project consists of...
Question 925: The project planning for the trade show is progressing on sc...
Question 926: At the time the risk register is first prepared, it should c...
Question 927: A Project Manager has been assigned to manage a project to d...
Question 928: As a project manager, not only must you be a leader, but you...
Question 929: Managing procurement relationships and monitoring contract p...
Question 930: You are the project manager for a two-year project that is n...
Question 931: Those who enter into a contractual agreement to provide serv...
Question 932: Which type of probability distribution is used to represent ...
Question 933: Your project management office implemented a project managem...
Question 934: Which technique is used in Perform Quantitative Risk Analysi...
Question 935: Project managers spend a great deal of time communicating wi...
Question 936: An input to the Plan Cost Management process is:...
Question 937: Analyzing the strengths, weaknesses, opportunities, and thre...
Question 938: The only Process Group that comprises processes that typical...
Question 939: You are a Project Manager who is involved in the procurement...
Question 940: The process of developing a detailed description of the proj...
Question 941: The Project Manager is working with the customer to gain for...
Question 942: The key benefit of the control communications process is to_...
Question 943: Which can be used to determine whether a process is stable o...
Question 944: High-level project risks are included in which document?...
Question 945: Taking out insurance in relation to risk management is calle...
Question 946: Which process is included in the Project Integration Managem...
Question 947: You are the Project Manager on a project where $4M US will b...
Question 948: The software development company has recently been awarded a...
Question 949: Stakeholders can be identified in later stages of the projec...
Question 950: One of the tools and techniques of the Manage Project Team p...
Question 951: The purpose of the Project Communications Management Knowled...
Question 952: A number of tools and techniques are helpful in the perform ...
Question 953: The stakeholder register should not be prepared only one tim...
Question 954: Which following item is NOT an input to control scope?...
Question 955: An output of the Manage Project Team process is:...
Question 956: Organizational process assets can be divided into which of t...
Question 957: You are developing a project charter and want to ensure that...
Question 958: Historical information is used______________...
Question 959: Which tool or technique is an examination of industry and sp...
Question 960: (Exhibit) Which of the following is the correct network diag...
Question 961: A weighting system is a tool for which area of procurement?...
Question 962: Which of the following is an output of the Plan Quality proc...
Question 963: The integrative nature of project management requires which ...
Question 964: You are managing a complex project for a new method of heati...
Question 965: The project planning is progressing. The team has involved t...
Question 966: Stakeholder engagement involves a number of critical activit...
Question 967: The specific technique for identifying a problem, discoverin...
Question 968: Any step recommended to bring expected future performance in...
Question 969: The process of establishing the policies, procedures, and do...
Question 970: In the initial stage of the project life cycle, the project'...
Question 971: The process of defining how the project scope will be valida...
Question 972: Increased attention to return on investment (ROI) now requir...
Question 973: The process of identifying specific actions to be performed ...
Question 974: Skills necessary for project management such as motivating t...
Question 975: Activity A has a duration of three days and begins on the mo...
Question 976: The sponsor is a key project stakeholder because he or she__...
Question 977: The project will be using a company to provide the technicia...
Question 978: In Plan Risk Management, which of the management plans deter...
Question 979: Units of measure, level of precision, level of accuracy, con...
Question 980: The area where the project manager can have the greatest imp...
Question 981: Project deliverables that have been completed and checked fo...
Question 982: You are a project manager for residential construction. As a...
Question 983: Which Manage Communications tool or technique focuses on ide...
Question 984: Which of the following tools and techniques is used to estim...
Question 985: You have assembled a core team to develop the project manage...
Question 986: Within your company's portfolio, your project is ranked in t...
Question 987: An approach to provide insight into the health of the projec...
Question 988: Assume you have been working with your sponsor to prepare yo...
Question 989: The key way for a project manager to promote optimum team pe...
Question 990: Which type of control tool identifies whether or not a proce...
Question 991: Assume that your actual costs are $800; your planned value i...
Question 992: Which schedule network analysis technique modifies the proje...
Question 993: When addressing roles and responsibilities,which item ensure...
Question 994: When a permitting agency takes longer than planned to issue ...
Question 995: An input required in Define Scope is an organizational:...
Question 996: Through whom do project managers accomplish work?...
Question 997: Which of the following is an enterprise environmental factor...
Question 998: The project is progressing well but has begun to experience ...
Question 999: The project scope baseline should be used in the identify ri...
Question 1000: Tools and techniques used in Direct and Manage Project Work ...
Question 1001: Which of the following correctly lists the configuration man...
Question 1002: Tools and techniques used for Plan Communications include th...
Question 1003: The zero duration of milestones in project planning occurs b...
Question 1004: When you established the change control board for your avion...
Question 1005: Requirements for formal deliverable acceptance are defined i...
Question 1006: Which process involves user cost estimates and the schedule ...
Question 1007: The project scope statement is important in scope control be...
Question 1008: What is used to define the accounts that the WBS and organiz...
Question 1009: Your company is embarking on a project to launch a new produ...
Question 1010: The contract in which the seller is reimbursed for all allow...
Question 1011: A special type of bar chart used in sensitivity analysis for...