Valid PMP Dumps shared by EduDump.com for Helping Passing PMP Exam! EduDump.com now offer the newest PMP exam dumps, the EduDump.com PMP exam questions have been updated and answers have been corrected get the newest EduDump.com PMP dumps with Test Engine here:
You are using earned value progress reporting for your current project in an effort to teach your software developers the benefits of earned value. You plan to display project results on the cafeteria bulletin board so that the team knows how the project is progressing. PV = $2,200 EV = $2,000 AC = $2,500 BAC = $10,000 What is the EAC for this project, and what does it represent?
Correct Answer: A
Explanation/Reference: Explanation: EAC is calculated as BAC/CPI (in this case, $10,000/0.80). It is now known that the project will cost more than the original estimate of $10,000. The project has been getting only 80 cents worth of work done for every dollar spent (CPI), and this information has been used to forecast total project costs. This approach assumes that performance for the remainder of the project will also be based on a CPI of 0.80.