Crosswind Custom Homes is building a customer's dream house. However, rain has delayed the finish by two weeks. The Project Manager evaluates the schedule and determines that by crashing, the project could be placed back on schedule. After discussing this with senior management, the Project Manager has decided to crash the project. By doing so, the Project Manager is adding what to the project?