Today, the primary cause of why projects are not completed on time and within cost and are terminated early is due to______________
Correct Answer: D
Explanation/Reference: Explanation: Behavioral reasons, rather than quantitative reasons, account for more project terminations because it is much more difficult to manage people than things. Issues such as poor morale, poor human relations, poor labor productivity, and no commitment from those involved in the project combine to thwart project success in many industries.