Valid SHRM-SCP Dumps shared by ExamDiscuss.com for Helping Passing SHRM-SCP Exam! ExamDiscuss.com now offer the newest SHRM-SCP exam dumps, the ExamDiscuss.com SHRM-SCP exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com SHRM-SCP dumps with Test Engine here:
The original deadline for a project was shortened by two weeks. Subsequently, the project manager learns that the project schedule must be shortened by another two weeks. Which action by the manager would best motivate the team to take on the new schedule?
Correct Answer: D
When a project schedule is shortened, motivating the team to meet the new deadlines can be challenging. Offering an incentive is an effective way to motivate the team, as it provides a tangible reward for their extra effort and dedication to meeting the new schedule. * Understanding Team Motivation: Incentives tap into intrinsic and extrinsic motivators, encouraging team members to go above and beyond their usual performance to meet the new deadlines. * Setting Clear Goals: Clearly communicate the new schedule and the specific criteria for earning the incentive. This helps the team understand what is expected and what they need to achieve to receive the reward. * Choosing Appropriate Incentives: The incentive should be meaningful and desirable to the team. It could be financial, such as bonuses, or non-financial, such as extra time off or recognition awards. * Maintaining Fairness and Transparency: Ensure that the incentive program is fair and transparent, * with all team members having an equal opportunity to earn the reward based on their contributions to meeting the new schedule. References: * SHRM guidelines on employee motivation and incentives * Best practices for managing project timelines and team performance