In analyzing a project for monthly status reporting, the project manager notices that the schedule performance index (SPI) is 0.75 and the cost performance index (CPI) is 1 25 The project manager must provide the first project status review soon and wants to emphasize that the project is under control How should the project manager report the project status to key stakeholders?
Correct Answer: A
the one that reflects the best practice of communicating project status to stakeholders, based on the earned value management (EVM) metrics and the project management plan. Reference: PMP Exam Set G - Q76 - This is a similar question with the same answer choices and a detailed explanation of why each option is correct or incorrect. It also provides a reference to the PMBOK Guide, Sixth Edition, page 267.