A project manager is working on an agile project. The organization decided to implement the Scrum framework. The project manager organized a workshop to explain the differences between traditional project artifacts and the Scrum approach. The most frequent question raised is what artifact will replace the project schedule. What should be me project manager's response?
Correct Answer: A
In the Scrum framework, the traditional project schedule is replaced by a combination of the sprint plan and the product roadmap. The sprint plan outlines the work to be performed during the sprint, which typically lasts 2-4 weeks, and includes the sprint goal, the set of product backlog items selected for the sprint, plus the plan for delivering the product increment and realizing the sprint goal. The product roadmap provides a longer-term view of where the product is headed and the milestones along the way. It is a strategic document that outlines the vision, direction, priorities, and progress of the product over time. : The information is aligned with the Scrum Guide and the principles outlined in the Project Management Institute's (PMI) Agile Practice Guide, which complements the PMBOKGuide and other PMI standards.