A project manager meets with the development team to estimate the time required to complete a software application. The software developers are new to the company, and they have never developed a similar application. Which estimation technique should the project manager recommend?
Correct Answer: C
Three-point estimating is a technique that can be particularly useful when there is uncertainty about the individual task estimates. It involves the development team providing optimistic, pessimistic, and most likely estimates for each task, which can then be used to calculate an expected duration for the entire project. This method is beneficial when the team lacks experience with similar projects, as it allows for a range of possible outcomes to be considered, which can lead to a more realistic and reliable estimate123. References: * Expert-Guided Software Project Estimation Techniques1 * Software Development Estimation: A Quick Guide - ProjectManager2 * Five keys to estimating - Project Management Institute3