Anew major road project is starting, and the contractor has contractually committed to submitting regular status reports and participating in integration meetings. Halfway through the project life cycle, the contractor stops participating in meetings and submitting reports, stating these items consume too much time. What should the project manager do first?
Correct Answer: C
The first step in addressing the contractor's failure to comply with the contractual commitments is to remind them of their obligations. This aligns with the best practices in project management, which emphasize communication and problem-solving as initial steps before escalating the issue or seeking legal recourse. It's important to address the issue directly with the contractor to understand their perspective and to work towards a mutually beneficial resolution. This approach is supported by the principles outlined in the PMBOKGuide, which advocate for proactive stakeholder engagement and communication management as essential components of project management. References: * PMBOKGuide - Sixth Edition * PMP Examination Content Outline - June 20191 * Professional in Business Analysis Reference Materials2