A project team is continually being asked by stakeholders to perform rework on their deliverables. The project manager discovers that this is due to poor initial quality. What should the project manager do?
Correct Answer: C
Repeated stakeholder-driven rework often indicates a mismatch between the team's quality assumptions and stakeholder expectations. The project manager should first facilitate alignment on quality criteria (C) so everyone shares the same definition of acceptable deliverables, standards, and acceptance measures. This includes clarifying requirements, acceptance criteria, and any relevant quality metrics or tolerances. Once "what quality means" is agreed, the team can adapt processes (reviews, testing, inspections, checklists, peer validation) to prevent defects and reduce rework. Simply telling the team to fix issues immediately (A) is reactive and treats symptoms rather than root causes; it can also create overtime pressure and further defects. Bringing in an SME (B) may help, but it does not solve expectation gaps unless the stakeholder definition of quality is clarified and adopted. A quality retrospective (D) is valuable for continuous improvement, but without agreed-upon quality expectations, the retrospective may generate actions that still miss what stakeholders actually need. Aligning on quality up front establishes a stable acceptance baseline, improves stakeholder satisfaction, and reduces costly rework cycles.