A project team identified a low-cost software product available for purchase that would drastically reduce the scope of development. The development manager has confirmed that this tool would fulfill the business need. What should the project manager do?
Correct Answer: D
The project manager's role is to ensure that the project meets its objectives while balancing the project constraints. In this scenario, the project team has identified a low-cost software product that could drastically reduce the scope of development. The development manager has confirmed that this tool would fulfill the business need. Therefore, the project manager should recommend this option to the product owner for consideration. The product owner is responsible for maximizing the value of the product resulting from the work of the development team. They are the ones who manage the product backlog and make the final decision on what should be included in it. References: Project Management Professional (PMP) Reference Materials, Professional in Business Analysis Reference Materials study guide.