In a software project using an agile approach, there have recently been work overruns. After assessing the situation, the project manager concluded that the overruns are occurring because of insufficiently refined product backlog items. What should the project manager do to correct this issue?
Correct Answer: B
A definition of ready (DoR) is a set of criteria or conditions that a product backlog item (PBI) must meet to be considered ready to be pulled into the sprint backlog1. A DoR ensures that the PBIs are clear, feasible, valuable, testable, and independent23. By creating a DoR for the backlog items, the project manager can avoid work overruns and ensure that the team can effectively tackle the tasks in the sprint2. References: Definition of Ready (DoR) [+ Key Components] | Atlassian Definition of Ready: Keeping Your Backlog in Check - Atlassian Community Ready or Not? Demystifying the Definition of Ready in Scrum