A project manager is implementing a project similar to a previous one that required strict adherence to occupational health and safety (OHS). Both projects are for the same client whose business environment is highly regulated. However, this time the client does not appear to be concerned about OHS requirements. What should the project manager do first?
Correct Answer: B
The project manager should first clarify expectations with the client before taking any further action. Open communication is a key part of stakeholder engagement and ensures alignment on mandatory safety requirements that may not be fully understood by all parties. Per the PMBOK Guide - Seventh Edition (Stakeholder and Planning Performance Domains), stakeholder consultation helps address risks and clarify scope elements like compliance. Assuming or ignoring requirements could lead to regulatory breaches. Option A is inappropriate and risky. Option C may cause unnecessary cost or complexity. Option D is premature without engaging the client first. References: PMBOK Guide - Seventh Edition, Stakeholder Engagement, Risk and Compliance PMI Code of Ethics and Professional Conduct - Responsibility ##############################################