A project manager is leading a project with a negative risk that has just become an issue. The risk was recorded and a response plan was set. However, a project team member proposes a response that differs from the response recorded in the risk management plan and believes it will be cheaper and equally effective. What should the project manager do?
Correct Answer: A
When a risk becomes an issue, the planned response provides a starting point, but the project manager should remain adaptive and choose the best response based on current information. If a credible alternative response is proposed, the appropriate step is to evaluate it with the project team (A) to confirm feasibility, effectiveness, side effects, and total impact (cost, schedule, quality, residual risks). This aligns with PMP decision-making: analyze options and select the response that best meets project objectives within constraints. Blindly adhering to the original plan (B) can be wasteful if circumstances have changed or a better option exists. Implementing immediately (C) is improper without validation and authorization; "cheaper" claims may ignore hidden costs or risks. Sending an email to the CCB (D) is premature; change control is appropriate if the selected response requires baseline changes or exceeds authority thresholds, but first the PM should conduct a structured evaluation to determine whether the new response is truly superior and what approvals are required.