A project manager manages a bridge construction project. The project manager has received a major change request from a regulatory stakeholder to add one branch of the bridge to the engineering design. The project manager prepared a change request, which was reviewed and accepted by the change control board (CCB). What should the project manager do now?
Correct Answer: C
After a change request is approved by the Change Control Board (CCB), the project manager should communicate the decision to the stakeholder who requested the change. This is an important step in the change management process as it ensures transparency and maintains trust with stakeholders. It also allows the stakeholder to understand that their request has been considered and integrated into the project, which is crucial for stakeholder engagement and satisfaction. : = The information is aligned with the PMBOK Guide's Change Management Process, which emphasizes the importance of communication with stakeholders after a decision has been made on a change request1. Additionally, the role of Business Analysts in change management includes ensuring that changes align with the organization's goals and objectives, which involves communicating approved changes to relevant stakeholders2.