Valid PMP Dumps shared by EduDump.com for Helping Passing PMP Exam! EduDump.com now offer the newest PMP exam dumps, the EduDump.com PMP exam questions have been updated and answers have been corrected get the newest EduDump.com PMP dumps with Test Engine here:
A project is 20% complete. The client has accepted a project order amendment that involves a major change. Without this major change, the project result will be useless for the client organization. What should the project manager do?
Correct Answer: B
If the client has already approved a change through a formal project order amendment, the project manager must initiate re-planning with the new scope. This aligns with adaptive and traditional approaches where major scope changes require updates to planning documents. Option A delays necessary rework. Option C addresses risk mitigation, but re-planning must begin first. Option D is unnecessary because the client has already accepted the amendment. References: PMBOK Guide - Seventh Edition, Planning and Delivery Performance Domains PMI Change Management Guidelines