A project is 20% complete. The client has accepted a project order amendment that involves a major change. Without this major change, the project result will be useless for the client organization. What should the project manager do?
Correct Answer: B
If the client has already approved a change through a formal project order amendment, the project manager must initiate re-planning with the new scope. This aligns with adaptive and traditional approaches where major scope changes require updates to planning documents. Option A delays necessary rework. Option C addresses risk mitigation, but re-planning must begin first. Option D is unnecessary because the client has already accepted the amendment. References: PMBOK Guide - Seventh Edition, Planning and Delivery Performance Domains PMI Change Management Guidelines