<< Prev Question Next Question >>

Question 4/171

In analyzing a project for monthly status reporting, the project manager notices that the schedule performance index (SPI) is 0.75 and the cost performance index (CPI) is 1.25. The project manager must provide the first project status review soon and wants to emphasize that the project is under control.
How should the project manager report the project status to key stakeholders?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (171q)
Question 1: A project manager is assigned to work on a large global proj...
Question 2: In a global project, the project manager has to plan and man...
Question 3: A project manager is building a team to work on a service in...
Question 4: In analyzing a project for monthly status reporting, the pro...
Question 5: A project manager has been assigned to a project that involv...
Question 6: In an effort to modernize the technology for a project, the ...
Question 7: During project execution, one of the project tasks is to cre...
Question 8: A project manager has been moved to a new division and is in...
Question 9: An experienced project manager is leading an enthusiastic te...
Question 10: A client has asked the project manager for the program statu...
Question 11: A new building project is in the middle of its life cycle. T...
Question 12: A network transformation project to increase efficiency and ...
Question 13: A company is initiating a project to enhance one of its exis...
Question 14: In the daily check-in meeting, a team member informs the pro...
Question 15: An organization is about to start a multiphased project. Due...
Question 16: In a project, one core team member tends to do all the work ...
Question 17: A client has requested that a product be implemented in 4 mo...
Question 18: A stakeholder on a project has a reputation for being easily...
Question 19: A project team is working to deliver a solution to manage na...
Question 20: A construction project for a nuclear power plant will reduce...
Question 21: A project manager has been assigned to a corporate project m...
Question 22: A project manager is meeting with the project sponsor regard...
Question 23: A local company is developing a new product and, for the fir...
Question 24: A project manager has been selected to deliver one of an org...
Question 25: An oil and gas project started without having acquired full ...
Question 26: A project team is executing a project to replace an existing...
Question 27: A project manager is managing a hybrid project. There is sof...
Question 28: While managing a project, the project manager has just notic...
Question 29: In a hybrid project, the customer has issued a contract that...
Question 30: After meeting with stakeholders, a project manager working a...
Question 31: A project manager has recently taken over a project and noti...
Question 32: A project manager is leading a project in an organization th...
Question 33: A project manager is assigned midway through a project. The ...
Question 34: A project manager has access to risk management tools but ch...
Question 35: A project manager is assigned to a project in a company that...
Question 36: A software system is being built for a company. Once the sys...
Question 37: A construction project to build a fish hatchery is in execut...
Question 38: After 35 years of service, a company's CEO has retired. The ...
Question 39: A project manager is newly assigned to the second phase ofan...
Question 40: Drag the interpersonal skill on the left to the correct scen...
Question 41: The project team is planning a schedule with limited informa...
Question 42: A project team is working hard to reach a milestone. The tea...
Question 43: A project manager is assigned to an agile project that has a...
Question 44: A team is working on a project using a hybrid approach, and ...
Question 45: A project manager has noticed that a critical team member is...
Question 46: A project sponsor wants to develop software that would have ...
Question 47: A project manager for a large, multiyear, industrial project...
Question 48: A project that has to be delivered by the targeted date has ...
Question 49: A bank is considering building another branch in one of thre...
Question 50: A project manager invites the company CEO, sponsor, team mem...
Question 51: In a weekly status meeting with the client, the project mana...
Question 52: A project manager is working as a servant leader for a pilot...
Question 53: A few stakeholders missed the session that was conducted to ...
Question 54: A project manager is working on a major construction project...
Question 55: A project manager is managing a complex research project wit...
Question 56: A construction company recently won the bid for a project to...
Question 57: A company is moving its headquarters to another city. The pr...
Question 58: A project needs to acquire a large volume of electrical supp...
Question 59: Product implementation portions of a project are nearing com...
Question 60: A company just started managing a project using an agile app...
Question 61: A hybrid project is experiencing several issues with both th...
Question 62: One of the team members is always late to the daily standup ...
Question 63: How can agile measurements improve upon predictive measureme...
Question 64: A project manager was recently assigned to a banking IT proj...
Question 65: A project manager is about to start a large-scale project wi...
Question 66: A project team delivered a critical deliverable to the custo...
Question 67: At the end of a project, the project manager was asked to pr...
Question 68: Company A has a culture of adhering to policies and procedur...
Question 69: A compliance strategy was created during the planning phase ...
Question 70: A project manager is assigned to a new project. The project ...
Question 71: An agile project started 6 months ago. Since the beginning o...
Question 72: A supplier informs the project manager that producing the qu...
Question 73: Stakeholders in some industries prefer to deal with programm...
Question 74: A senior project manager is assigned to lead a team of proje...
Question 75: A project manager is struggling to figure out the performanc...
Question 76: A project manager receives information in preparation for re...
Question 77: A company has decided to implement a new archiving system. A...
Question 78: A hybrid project has just deployed, and the project manager ...
Question 79: A project manager was recently assigned to a new project tha...
Question 80: A client's company announces a reorganization, which include...
Question 81: A customer asks the project manager about opportunities to c...
Question 82: A project manager has received a new request to integrate mo...
Question 83: The project manager of a large construction project discover...
Question 84: A bank wantsto initiate a new service for its customers that...
Question 85: Team members are having a discussion with the project manage...
Question 86: A project manager has been assigned to an education project ...
Question 87: A project manager is working with the product owner and cust...
Question 88: The client will not agree to closure, claiming that the proj...
Question 89: A company is transitioning from a predictive to an agile app...
Question 90: A project manager is working on a project that is required t...
Question 91: A company is transitioning from a predictive approach to an ...
Question 92: A project manager works with a global virtual team. The team...
Question 93: A project manager is in charge of a software development pro...
Question 94: An information technology (IT) team is responsible for the v...
Question 95: During project execution, the client requires several change...
Question 96: A client wants to create an innovative software for the trav...
Question 97: A laboratory is launching a new product, defined to be execu...
Question 98: A project team consists of members based in country A and su...
Question 99: During the final stage of the launch for a new design, team ...
Question 100: The sponsor of a newly formed agile project is struggling to...
Question 101: A project manager is executing a commercial building project...
Question 102: A project using a hybrid approach to migrate from a current ...
Question 103: A project manager collects various pieces of information and...
Question 104: Some of the team members who are working on a new software t...
Question 105: A project is halfway through its execution phase. The qualit...
Question 106: One of the key stakeholders on the project team reaches out ...
Question 107: An agile project is approaching its first release date, and ...
Question 108: A scrum team's daily meetings are conducted by teleconferenc...
Question 109: Halfway through project execution, stakeholders ask for equi...
Question 110: An agile project team discovers that they are unable to impl...
Question 111: A project team member is sick and will not be able to return...
Question 112: A project manager is leading a global project with resources...
Question 113: A leader from project B consistently reaches out to a team m...
Question 114: During the initiating phase of a project, a key stakeholder ...
Question 115: An agile project manager notices that one of the team member...
Question 116: A project team is in the planning phase of a product migrati...
Question 117: A team member has experienced personal conflicts on past pro...
Question 118: An agile senior project team member suddenly resigns from th...
Question 119: A project manager has recently been asked to take over an ex...
Question 120: An external project manager is managing the construction of ...
Question 121: A project manager is performing earned value management (EVM...
Question 122: A project sponsor has requested that the project manager rep...
Question 123: A project manager is assigned to a project. There was a lot ...
Question 124: A project manager has taken over an agile project. There hav...
Question 125: A project manager is leading an agile project in an organiza...
Question 126: Aretail chain is evaluating a project to replace payment sys...
Question 127: A project team consists of eight resources working on a comp...
Question 128: In the middle of an iteration, an agile team working on the ...
Question 129: During the execution phase of a project, one of the customer...
Question 130: An agile coach and technical writer for a globally distribut...
Question 131: A project presently in the testing stage is nearing the clos...
Question 132: On a project with multiple international locations, a trend ...
Question 133: During project execution, the project manager observes lower...
Question 134: A project is about to start with a global project team. Trav...
Question 135: A project manager is asked to implement a hybrid approach th...
Question 136: A mid-size capital project has shared resources from the com...
Question 137: A project team began working on a complex project that invol...
Question 138: A project sponsor has requested atrend analysis of all risks...
Question 139: During a project's closing phase, the project manager identi...
Question 140: A project has completed design activities ahead of schedule....
Question 141: An experienced project manager is working on a complex hybri...
Question 142: A project manager has been moved to a new division and is in...
Question 143: A project manager has a team of shared resources from other ...
Question 144: The project team has been exposed to a large number of stake...
Question 145: A risk was raised during the initiation of a project. The su...
Question 146: A project has been running successfully for 2 months. At a r...
Question 147: One team member is complaining about an agreement made durin...
Question 148: An agile project is running its second iteration out of six....
Question 149: A project manager acquired information from the market that ...
Question 150: A project manager realizes that the team members are new to ...
Question 151: In a highly politicized organizational environment, the stak...
Question 152: A verbal announcement is made that the new team member joini...
Question 153: A company plans to initiate a project involving a new techno...
Question 154: A project manager has noticed that the performance of a new ...
Question 155: A healthcare organization hired a new compliance specialist ...
Question 156: In an agile team, some of the team members are coming forwar...
Question 157: After the merger of two large companies, a project manager i...
Question 158: A project is in the middle of the fifth iteration. Due to a ...
Question 159: A project manager prepared a project benefits management pla...
Question 160: A project team is in the planning stage and has prepared a l...
Question 161: A project manager has been managing a highly complex project...
Question 162: While following up on a deliverable, a team member expresses...
Question 163: In an agile project, the team planned to complete 40 story p...
Question 164: A project manager is managing a technical project that requi...
Question 165: A project manager is managing a project with team members wh...
Question 166: A project manager has recently joined a small company. The c...
Question 167: A defect is identified during user acceptance testing that c...
Question 168: A company has been following a predictive approach and alway...
Question 169: A software project using an agile approach is facing quality...
Question 170: Two members of a new project team disagree on the best appro...
Question 171: From previous lessons learned working with a client, a proje...