A project manager is working on a major construction project. Part of the agreed-upon plan was to use a cloud-based system with a server that runs on high-speed internet service since most of the team members work virtually. The company needs to reduce operating costs as much as possible and management insists that the project will now use a system running on a conventional dial-up service. What should the project manager do next?
Correct Answer: D
Explanation The project manager should evaluate the impact of this decision on the project scope, schedule, cost, quality, risk, and stakeholder satisfaction. The project manager should also communicate with management about the potential benefits and drawbacks of using a conventional dial-up service instead of a cloud-based system. The project manager should present alternative solutions and recommendations based on the analysis. The other options are not the best actions to take in this situation, as they do not address the root cause of the problem or seek to find a mutually acceptable solution. References: = A Guide to the Project Management Body ofKnowledge (PMBOK Guide) - Seventh Edition, Chapter 4: Project Performance, Section 4.2: Monitor and Control Project Work, Page 105-106.