Valid PMP Dumps shared by ExamDiscuss.com for Helping Passing PMP Exam! ExamDiscuss.com now offer the newest PMP exam dumps, the ExamDiscuss.com PMP exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PMP dumps with Test Engine here:
A project manager is assigned to work on a large global project. The resources for the project are dispersed among different organizations and countries. After the projectkick-off meeting, the project manager learns that many virtual team members are unable to join the regular project update meetings. Their absence will impact the overallproject schedule. What immediate corrective action should the project manager take?
Correct Answer: A
Explanation The project manager should discuss the issue with the virtual team members and revise the communications management plan as an immediate corrective action. This is because the project manager needs to understand the reasons why the virtual team members are unable to join the regular project update meetings and find a solution that works for them. The project manager should also update the communications management plan to reflect the changes in the communication requirements, methods, frequency, and tools for the virtual team members. The project manager should ensure that the communication plan is aligned with the project objectives, stakeholder expectations, and organizational culture. Option B is not a good action, as escalating this issue to the virtual team members' supervisors may not be appropriate or effective. It may also create conflict, resentment, and distrust among the team members. The project manager should try to resolve the issue directly with the virtual team members and not involve their supervisors without their consent or agreement. Option C is not a good action, as adding this issue to the risk management plan and taking action if it persists is a passive and delayed approach. The project manager should try to prevent or mitigate the issue as soon as possible and not wait until it becomes a risk that affects the project performance. The project manager should also not treat the issue as a risk, but as a problem that needs to be solved. Option D is not a good action, as discussing the issue with the project sponsors and adding this as an issue in the issue log is a reactive and formal approach. The project manager should try to solve the issue informally and collaboratively with the virtual team members and not escalate it to the project sponsors unless necessary. The project manager should also not document the issue in the issue log, but in the communication plan. References: [PMBOK Guide], 6th edition, page 368, section 10.1 [PMP Exam Content Outline], page 10, task 5 under domain 2