A new building project is in the middle of its life cycle. The municipality informs the project manager that due to new regulations, the parking lot around theproject has to accommodate twice the number of cars than was initially planned. What should the project manager do next?
Correct Answer: A
Explanation According to the PMBOK Guide, 6th edition, page 123, the project manager is responsible for managing the project scope and ensuring that the project deliverables meet the agreed requirements and expectations of the customer and other stakeholders. If the project manager receives a request for a change in the project scope, such as the parking lot size, the project manager should follow the change management process, which involves assessing the impact of the change on the project objectives, constraints, and assumptions, and consulting with the executive sponsors and other key stakeholders to determine the best course of action. The project manager should not reject, accept, or implement the change without following the changemanagement process, as this may lead to scope creep, rework, waste, or poor quality. References: PMBOK Guide, 6th edition, page 123 Free PMP Practice Exam Questions - 120 Sample Test Questions