A company just started managing a project using an agile approach. Due to this change, the general manager is worried about the scope definition processfor upcoming projects. What should the project manager do to ensure the project scope is completely defined?
Correct Answer: B
Explanation The project manager should help the sponsors and stakeholders create a clear and shared product vision that describes the purpose, features, and benefits of the product. The product vision guides the project scope and provides a common understanding of what the project aims to deliver. The project manager should also facilitate collaboration and communication between the team and the product owner, who is responsible fordefining and prioritizing the product requirements. The team and the product owner should work together to refine and validate the requirements throughout the project, using feedback loops and iterative delivery. This way, the project scope is continuously aligned with the customer needs and expectations, and any changes or uncertainties are managed effectively. References: (Project Management Professional (PMP) Reference Materials source and documents) A Guide to the Project Management Body of Knowledge (PMBOK Guide) - Seventh Edition, Chapter 2: Value Delivery System, Section 2.3.1: Agile Principles and Values Agile Practice Guide, Chapter 3: Life Cycle Selection, Section 3.1: Introduction to Life Cycles [PMP Exam Content Outline], Domain II: Process, Task 2: Determine project scope.