<< Prev Question Next Question >>

Question 58/171

A project needs to acquire a large volume of electrical supplies on a weekly delivery cycle. There are many suppliers interested in partnering, so the project manager feels confident they can negotiate a goodprice.
What should the project manager do first in order to ensure the best overall value in the future contract?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (171q)
Question 1: A project manager is assigned to work on a large global proj...
Question 2: In a global project, the project manager has to plan and man...
Question 3: A project manager is building a team to work on a service in...
Question 4: In analyzing a project for monthly status reporting, the pro...
Question 5: A project manager has been assigned to a project that involv...
Question 6: In an effort to modernize the technology for a project, the ...
Question 7: During project execution, one of the project tasks is to cre...
Question 8: A project manager has been moved to a new division and is in...
Question 9: An experienced project manager is leading an enthusiastic te...
Question 10: A client has asked the project manager for the program statu...
Question 11: A new building project is in the middle of its life cycle. T...
Question 12: A network transformation project to increase efficiency and ...
Question 13: A company is initiating a project to enhance one of its exis...
Question 14: In the daily check-in meeting, a team member informs the pro...
Question 15: An organization is about to start a multiphased project. Due...
Question 16: In a project, one core team member tends to do all the work ...
Question 17: A client has requested that a product be implemented in 4 mo...
Question 18: A stakeholder on a project has a reputation for being easily...
Question 19: A project team is working to deliver a solution to manage na...
Question 20: A construction project for a nuclear power plant will reduce...
Question 21: A project manager has been assigned to a corporate project m...
Question 22: A project manager is meeting with the project sponsor regard...
Question 23: A local company is developing a new product and, for the fir...
Question 24: A project manager has been selected to deliver one of an org...
Question 25: An oil and gas project started without having acquired full ...
Question 26: A project team is executing a project to replace an existing...
Question 27: A project manager is managing a hybrid project. There is sof...
Question 28: While managing a project, the project manager has just notic...
Question 29: In a hybrid project, the customer has issued a contract that...
Question 30: After meeting with stakeholders, a project manager working a...
Question 31: A project manager has recently taken over a project and noti...
Question 32: A project manager is leading a project in an organization th...
Question 33: A project manager is assigned midway through a project. The ...
Question 34: A project manager has access to risk management tools but ch...
Question 35: A project manager is assigned to a project in a company that...
Question 36: A software system is being built for a company. Once the sys...
Question 37: A construction project to build a fish hatchery is in execut...
Question 38: After 35 years of service, a company's CEO has retired. The ...
Question 39: A project manager is newly assigned to the second phase ofan...
Question 40: Drag the interpersonal skill on the left to the correct scen...
Question 41: The project team is planning a schedule with limited informa...
Question 42: A project team is working hard to reach a milestone. The tea...
Question 43: A project manager is assigned to an agile project that has a...
Question 44: A team is working on a project using a hybrid approach, and ...
Question 45: A project manager has noticed that a critical team member is...
Question 46: A project sponsor wants to develop software that would have ...
Question 47: A project manager for a large, multiyear, industrial project...
Question 48: A project that has to be delivered by the targeted date has ...
Question 49: A bank is considering building another branch in one of thre...
Question 50: A project manager invites the company CEO, sponsor, team mem...
Question 51: In a weekly status meeting with the client, the project mana...
Question 52: A project manager is working as a servant leader for a pilot...
Question 53: A few stakeholders missed the session that was conducted to ...
Question 54: A project manager is working on a major construction project...
Question 55: A project manager is managing a complex research project wit...
Question 56: A construction company recently won the bid for a project to...
Question 57: A company is moving its headquarters to another city. The pr...
Question 58: A project needs to acquire a large volume of electrical supp...
Question 59: Product implementation portions of a project are nearing com...
Question 60: A company just started managing a project using an agile app...
Question 61: A hybrid project is experiencing several issues with both th...
Question 62: One of the team members is always late to the daily standup ...
Question 63: How can agile measurements improve upon predictive measureme...
Question 64: A project manager was recently assigned to a banking IT proj...
Question 65: A project manager is about to start a large-scale project wi...
Question 66: A project team delivered a critical deliverable to the custo...
Question 67: At the end of a project, the project manager was asked to pr...
Question 68: Company A has a culture of adhering to policies and procedur...
Question 69: A compliance strategy was created during the planning phase ...
Question 70: A project manager is assigned to a new project. The project ...
Question 71: An agile project started 6 months ago. Since the beginning o...
Question 72: A supplier informs the project manager that producing the qu...
Question 73: Stakeholders in some industries prefer to deal with programm...
Question 74: A senior project manager is assigned to lead a team of proje...
Question 75: A project manager is struggling to figure out the performanc...
Question 76: A project manager receives information in preparation for re...
Question 77: A company has decided to implement a new archiving system. A...
Question 78: A hybrid project has just deployed, and the project manager ...
Question 79: A project manager was recently assigned to a new project tha...
Question 80: A client's company announces a reorganization, which include...
Question 81: A customer asks the project manager about opportunities to c...
Question 82: A project manager has received a new request to integrate mo...
Question 83: The project manager of a large construction project discover...
Question 84: A bank wantsto initiate a new service for its customers that...
Question 85: Team members are having a discussion with the project manage...
Question 86: A project manager has been assigned to an education project ...
Question 87: A project manager is working with the product owner and cust...
Question 88: The client will not agree to closure, claiming that the proj...
Question 89: A company is transitioning from a predictive to an agile app...
Question 90: A project manager is working on a project that is required t...
Question 91: A company is transitioning from a predictive approach to an ...
Question 92: A project manager works with a global virtual team. The team...
Question 93: A project manager is in charge of a software development pro...
Question 94: An information technology (IT) team is responsible for the v...
Question 95: During project execution, the client requires several change...
Question 96: A client wants to create an innovative software for the trav...
Question 97: A laboratory is launching a new product, defined to be execu...
Question 98: A project team consists of members based in country A and su...
Question 99: During the final stage of the launch for a new design, team ...
Question 100: The sponsor of a newly formed agile project is struggling to...
Question 101: A project manager is executing a commercial building project...
Question 102: A project using a hybrid approach to migrate from a current ...
Question 103: A project manager collects various pieces of information and...
Question 104: Some of the team members who are working on a new software t...
Question 105: A project is halfway through its execution phase. The qualit...
Question 106: One of the key stakeholders on the project team reaches out ...
Question 107: An agile project is approaching its first release date, and ...
Question 108: A scrum team's daily meetings are conducted by teleconferenc...
Question 109: Halfway through project execution, stakeholders ask for equi...
Question 110: An agile project team discovers that they are unable to impl...
Question 111: A project team member is sick and will not be able to return...
Question 112: A project manager is leading a global project with resources...
Question 113: A leader from project B consistently reaches out to a team m...
Question 114: During the initiating phase of a project, a key stakeholder ...
Question 115: An agile project manager notices that one of the team member...
Question 116: A project team is in the planning phase of a product migrati...
Question 117: A team member has experienced personal conflicts on past pro...
Question 118: An agile senior project team member suddenly resigns from th...
Question 119: A project manager has recently been asked to take over an ex...
Question 120: An external project manager is managing the construction of ...
Question 121: A project manager is performing earned value management (EVM...
Question 122: A project sponsor has requested that the project manager rep...
Question 123: A project manager is assigned to a project. There was a lot ...
Question 124: A project manager has taken over an agile project. There hav...
Question 125: A project manager is leading an agile project in an organiza...
Question 126: Aretail chain is evaluating a project to replace payment sys...
Question 127: A project team consists of eight resources working on a comp...
Question 128: In the middle of an iteration, an agile team working on the ...
Question 129: During the execution phase of a project, one of the customer...
Question 130: An agile coach and technical writer for a globally distribut...
Question 131: A project presently in the testing stage is nearing the clos...
Question 132: On a project with multiple international locations, a trend ...
Question 133: During project execution, the project manager observes lower...
Question 134: A project is about to start with a global project team. Trav...
Question 135: A project manager is asked to implement a hybrid approach th...
Question 136: A mid-size capital project has shared resources from the com...
Question 137: A project team began working on a complex project that invol...
Question 138: A project sponsor has requested atrend analysis of all risks...
Question 139: During a project's closing phase, the project manager identi...
Question 140: A project has completed design activities ahead of schedule....
Question 141: An experienced project manager is working on a complex hybri...
Question 142: A project manager has been moved to a new division and is in...
Question 143: A project manager has a team of shared resources from other ...
Question 144: The project team has been exposed to a large number of stake...
Question 145: A risk was raised during the initiation of a project. The su...
Question 146: A project has been running successfully for 2 months. At a r...
Question 147: One team member is complaining about an agreement made durin...
Question 148: An agile project is running its second iteration out of six....
Question 149: A project manager acquired information from the market that ...
Question 150: A project manager realizes that the team members are new to ...
Question 151: In a highly politicized organizational environment, the stak...
Question 152: A verbal announcement is made that the new team member joini...
Question 153: A company plans to initiate a project involving a new techno...
Question 154: A project manager has noticed that the performance of a new ...
Question 155: A healthcare organization hired a new compliance specialist ...
Question 156: In an agile team, some of the team members are coming forwar...
Question 157: After the merger of two large companies, a project manager i...
Question 158: A project is in the middle of the fifth iteration. Due to a ...
Question 159: A project manager prepared a project benefits management pla...
Question 160: A project team is in the planning stage and has prepared a l...
Question 161: A project manager has been managing a highly complex project...
Question 162: While following up on a deliverable, a team member expresses...
Question 163: In an agile project, the team planned to complete 40 story p...
Question 164: A project manager is managing a technical project that requi...
Question 165: A project manager is managing a project with team members wh...
Question 166: A project manager has recently joined a small company. The c...
Question 167: A defect is identified during user acceptance testing that c...
Question 168: A company has been following a predictive approach and alway...
Question 169: A software project using an agile approach is facing quality...
Question 170: Two members of a new project team disagree on the best appro...
Question 171: From previous lessons learned working with a client, a proje...