A project team consists of members based in country A and subject matter experts (SMEs) based in country B with a 12-hour time difference. What can the project manager do to improve interactions between the team members in both countries?
Correct Answer: C
Explanation
According to the PMBOK Guide, 7th edition, communication management is the process of ensuring timely and appropriate collection, creation, distribution, storage, retrieval, management, monitoring, and the ultimate disposition of project information. Communication management involves planning, managing, and monitoring communications throughout the project life cycle. Communication management also involves considering the communication needs, preferences, and cultural differences of the project stakeholders. In this question, the project team consists of members based in country A and subject matter experts (SMEs) based in country B with a 12-hour time difference. The question asks what the project manager can do to improve interactions between the team members in both countries.
Based on this information, the best answer is option C, which is to identify virtual communication methods and arrange for regular team meetings accordingly. This is because identifying virtual communication methods and arranging for regular team meetings is a communication management practice that can help the project manager to facilitate effective and efficient communication and collaboration among geographically dispersed team members. Virtual communication methods are tools and techniques that enable remote communication and interaction, such as email, phone, video conferencing, instant messaging, online forums, and social media.
Regular team meetings are sessions that allow the team members to share information, provide updates, resolve issues, make decisions, and give feedback. Identifying virtual communication methods and arranging for regular team meetings can help the project manager to overcome the challenges posed by the time difference, as well as to build trust, rapport, and teamwork among the team members in both countries.
Option A, which is to ensure full participation of both the product owner and business SMEs in scope planning sessions, is not a good answer. This is because ensuring full participation of both the product owner and business SMEs in scope planning sessions may not be relevant or sufficient to improve interactions between the team members in both countries. Scope planning sessions are sessions that involve defining and documenting the project scope, deliverables, assumptions, and constraints. Scope planning sessions may not require the participation of all team members, as some team members may not be involved in the scope definition or validation. Scope planningsessions may not address the communication and collaboration issues that may arise from the time difference, as they may not occur frequently or regularly.
Option B, which is to explore the opportunity to have both teams colocated, is not a good answer. This is because exploring the opportunity to have both teams colocated may not be feasible or cost-effective, as it may involve additional expenses, logistics, and risks. Colocating both teams may also disrupt their work environment, productivity, and motivation. Colocating both teams may not be necessary, as virtual communication methods and regular team meetings can provide a similar level of interaction and collaboration.
Option D, which is to plan for frequent face-to-face meetings, is not a good answer. This is because planning for frequent face-to-face meetings may not be possible or practical, as it may involve travel, time, and budget constraints. Face-to-face meetings may also expose the team members to health and safety risks, especially during the COVID-19 pandemic. Face-to-face meetings may not be preferable, as some team members may prefer virtual communication methods or have personal or professional commitments that prevent them from traveling. Face-to-face meetings may not be superior, as virtual communication methods and regular team meetings can offer comparable benefits and outcomes. References: PMBOK Guide, 7th edition, Chapter 8:
Communication1; PMI, 2023, PMP Exam Content Outline, Domain II: Process, Task 10: Plan and manage project/phase communications.