A project manager is asked to implement a hybrid approach that will replace a predictive approach on an upcoming project.How should the project manageradjust their responsibilities accordingly?
Correct Answer: C
Explanation
= The project manager should adjust their responsibilities accordingly by becoming a servant leader by supporting team collaboration and removing impediments when implementing a hybrid approach that will replace a predictive approach on an upcoming project. According to the PMBOK Guide, a hybrid approach is a project management approach that combines predictive and adaptive (agile) practices to fit the project context, complexity, and uncertainty[1]. A hybrid approach requires the project manager to balance the need for planning and control with the need for flexibility and responsiveness to changing customer needs and expectations[1]. Therefore, the project manager should adopt a servant leadership style, which is a leadership style that focuses on empowering and serving the team rather than directing and controlling them[1]. A servant leader supports team collaboration by facilitating communication, feedback, and decision making among the team members and other stakeholders[1]. A servant leader also removes impediments by identifying and resolving issues that prevent the team from delivering value to the customer[1]. By becoming a servant leader, the project manager can enhance the team performance and satisfaction, and deliver customer value in a hybrid approach. The other options are not appropriate for this situation, as they do not reflect the role of the project manager in a hybrid approach.
Introducing new communication tools to the project team members is a possible action that the project manager can take, but it is not the main responsibility of the project manager in a hybrid approach.
Communication tools are only effective if they are used to support team collaboration and customer feedback, which are the core values of a hybrid approach[1].
Requesting a scrum master to focus on the collaboration while the project manager focuses on the coordination is a wrong way to implement a hybrid approach, as it creates a role conflict and a lack of alignment between the project manager and the scrum master. A scrum master is a role in an agile framework that coaches and guides the team and the product owner in applying agile principles and practices[1]. Ascrum master is not a substitute for the project manager, nor is the project manager a superior to the scrum master. In a hybrid approach, the project manager and the scrum master should work together to ensure the project objectives and customer expectations are met, and to share the responsibilities of collaboration and coordination[1].
Delegating coordination activities to the product owner so the project manager can focus on managing collaboration is a wrong way to implement a hybrid approach, as it creates a role overload and a lack of accountability for the product owner. A product owner is a role in an agile framework that represents the voice of the customer and defines and prioritizes the product backlog[1]. A product owner is not responsible for coordinating the project activities, resources, and stakeholders, which are the primary functions of the project manager. In a hybrid approach, the project manager and the product owner should work together to ensure the product vision and scope are aligned with the project goals and constraints, and to share the responsibilities of collaboration and coordination[1].
References: [1]: PMBOK Guide, 7th edition, pages 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25, 26, 27, 28,