During project execution, the client requires several changes that will impact the project's duration. The project manager needs to apply fast-tracking techniques to accelerate the schedule, but the team is concerned about working overtime. What should the project manager do to motivate the team?
Correct Answer: C
Explanation Fast-tracking is a schedule compression technique that involves performing activities in parallel that were originally planned to be performed sequentially1. This can increase the risk of rework and errors, as well as the stress and workload of the team members2. To motivate the team, the project manager should introduce team-building activities that can enhance the team's trust, collaboration, and morale3. Team-building activities can also help the team cope with the challenges and uncertainties of fast-tracking4. References: 1: PMBOK Guide, 6th edition, p. 215 2: PMBOK Guide, 6th edition, p. 216 3: PMBOK Guide, 6th edition, p. 336 4: PMBOK Guide, 6th edition, p. 337