A project is halfway through its execution phase. The quality specifications for the project deliverables are formally accepted. However, a key stakeholder is dissatisfied, stating that the deliverables do not meet the quality specifications. What should the project manager do in this situation?
Correct Answer: B
Explanation The requirements traceability matrix is a tool that links the project requirements to the project scope, deliverables, quality criteria, and verification methods. It helps to ensure that the project meets the stakeholder expectations and the quality standards. By reviewing the matrix and conducting inspections, the project manager can identify any gaps or discrepancies between the quality specifications and the deliverables, and take corrective actions if needed. The other options are not appropriate in thissituation, as they do not address the root cause of the stakeholder's dissatisfaction or the quality issue. References: PMBOK Guide, 7th edition, page 101, 103, 108.