A client wants to create an innovative software for the travel industry using an agile approach. A project manager from the company was assigned to work on the details and estimates as requested by the client. What should the project manager do before sending the information to the client?
Correct Answer: D
Explanation The project manager should work with the team to understand their views and add the appropriate dependencies and risks before sending the information to the client because this is consistent with the agile principles and values. The agile approach emphasizes collaboration, communication, and feedback among the project team and stakeholders. The project manager should involve the team in the estimation and planning process, as they have the best knowledge and experience of the work to be done. The project manager should also identify and analyze the dependencies and risks that may affect the project scope, schedule, cost, and quality, and communicate them to the client. This will help to establish trust, transparency, and alignment between the project team and the client, and enable them to respond to changes and uncertainties effectively. References: A Guide to the Project Management Body of Knowledge (PMBOK Guide) - Seventh Edition, Chapter 2.2.2, page 28 Agile Practice Guide, Chapter 2.1.1, page 14 PMP Exam Content Outline, Domain II: Planning, Task 2