Valid PMP Dumps shared by ExamDiscuss.com for Helping Passing PMP Exam! ExamDiscuss.com now offer the newest PMP exam dumps, the ExamDiscuss.com PMP exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PMP dumps with Test Engine here:
A project manager acquired information from the market that would reduce the business value being delivered by an ongoing project. Based on that information, the project manager believes the project shouldbe stopped. How should the project manager handle the situation?
Correct Answer: B
Explanation The project manager should handle the situation by having a discussion with the sponsor and recommending the project business value be reassessed. This is because the project manager is not authorized to cancel the project, but should communicate the new information to the sponsor and suggest a reevaluation of the project benefitsand alignment with the organizational strategy. This approach is consistent with the principles of stakeholder engagement, communication management, and business environment in project management. References: PMBOK Guide, 6th edition, pages 33-34, 51-52, 513-514. PMP Exam Content Outline, June 2019, pages 6-7, 10-11, 16-17.