You manage a design-build project to renovate a new office space, including infrastructure upgrades. At the 60% design phase, the design-build contractor's project estimate is over budget and contingency. What should be done first to address the issue?
Correct Answer: D
The first step should be to investigate the reasons for being over budget (D) before making major project changes. * A cost overrun could be due to inaccurate estimates, scope changes, or unforeseen conditions. Understanding the cause allows for informed decision-making. * Why not other options? * (A) Delaying a portion of the project may not be necessary and could lead to inefficiencies. * (B) Seeking a change order should only be done after understanding why costs have increased. * (C) Removing infrastructure upgrades without proper evaluation could negatively impact long-term functionality.