You are the business analyst for your organization. Management realizes that a proposed solution has risks that may cause the entire project to fail. They would like you to prioritize the requirements with maximum risks first so that if the project fails, there is little loss of capital in the project implementation. What requirements prioritization approach is management asking you to create in this instance?
Correct Answer: B
Explanation Business or technical risk is a requirements prioritization approach that involves ranking the requirements based on the potential negative consequences or uncertainties associated with their implementation or non-implementation. This approach can help to identify and mitigate the most critical risks early in the project and reduce the likelihood of project failure. Business or technical risk can be assessed by considering factors such as the impact on the business value, the feasibility of the solution, the complexity of the requirements, the dependencies among the requirements, the volatility of the requirements, and the stakeholder satisfaction. Business or technical risk is one of the common criteria for requirements prioritization, as it helps to balance the benefits and costs of the requirements1234. References: 1: Requirement prioritization3 2: The Ultimate Guide to Requirements Prioritization4 3: Business Analysis Techniques: Prioritizing Requirements5 4: Requirements Prioritization: How to Prioritize Requirements