Valid CBAP Dumps shared by ExamDiscuss.com for Helping Passing CBAP Exam! ExamDiscuss.com now offer the newest CBAP exam dumps, the ExamDiscuss.com CBAP exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com CBAP dumps with Test Engine here:
A company with a big information technology (IT) department has hired a lead business analyst (BA) to enhance its business analysis practices. The lead BA discovers that sponsors are not satisfied with project outcomes. Developers complain about incomplete, ambiguous, and changing requirements. All stakeholders, including project managers, are blaming long cycles of analysis for the delays. The business analysts, in turn, feel overwhelmed with the number of projects and frustrated by the lack of collaboration from reviewers of their deliverables. All of the evidence is anecdotal and none of the groups could strongly substantiate their opinions. Even after dozens of reviews, some stakeholders refuse to sign off on the requirements specification documents because of a few questionable requirements. This puts the projects at risk and creates tension between the participants. What should the lead BA do first?
Correct Answer: C
Explanation The lead BA should track approvals at the level of individual requirements, as this is the first step to address the root cause of the problem, which is the lack of agreement and clarity on the requirements. By tracking approvals at the level of individual requirements, the lead BA can identify which requirements are causing the most disagreement or confusion, and focus on resolving them with the relevant stakeholders. This can also help to reduce the number of reviews and sign-offs needed, as well as the time and effort spent on them. Tracking approvals at the level of individual requirements can also provide objective evidence of the progress and quality of the requirements, and support the communication and collaboration among the stakeholders. The other options are not the best actions to take first. Escalating the problem to the executive management may be necessary at some point, but it is not the first thing to do, as it may create more conflict and pressure, and undermine the lead BA's credibility and authority. Setting limits on duration of sign-offs and the number of reviews may be helpful to manage the expectations and deadlines, but it does not address the underlying issue of the requirements quality and agreement. Offering the stakeholders incentives to sign off documents sooner may be counterproductive, as it may encourage hasty or superficial approvals, and compromise the validity and value of the requirements. References: The answer can be verified from the following sources: A Guide to the Business Analysis Body of Knowledge (BABOK Guide) Version 3, Chapter 6: Requirements Life Cycle Management, p. 202-203, 207-208, 211-212. Business Analysis for Practitioners: A Practice Guide, Chapter 4: Requirements Life Cycle Management, p. 97-98, 101-102, 105-106.