Which of the following process models needs to complete each set of tasks in one phase before moving into the next phase in a project development life cycle?
Correct Answer: D
Explanation
The waterfall model is a linear and sequential process model that needs to complete each set of tasks in one phase before moving into the next phase in a project development life cycle. The phases are typically requirements, design, implementation, verification, and maintenance. The waterfall model is suitable for projects with well-defined and stable requirements, clear objectives, and minimal risks of changes. References
:
Certified Business Analysis Professional (CBAP) | Coursera, Course 1, Week 2, Video: "Waterfall Model" CERTIFIED BUSINESS ANALYSIS PROFESSIONAL, Page 9, Section: "Review the Exam Blueprint"