Which one of the following diagrams when properly laid out is always laid in a left to right display to properly reflect the chronology of all project work?
Correct Answer: B
Explanation A project schedule network diagram is a graphical representation of the logical relationships among the project activities. It shows the dependencies, sequence, and duration of all the activities in a project. A project schedule network diagram is always laid out in a left to right display to properly reflect the chronology of all project work. The diagram can be drawn using different methods, such as the precedence diagramming method (PDM), the arrow diagramming method (ADM), or the graphical evaluation and review technique (GERT). References: Project Schedule Network Diagrams from the Project Management Body of Knowledge (PMBOK Guide) - Sixth Edition Schedule Network Analysis from the Business Analysis Body of Knowledge (BABOK Guide) - Version 3