You are the business analyst for the NHQ Project. You have identified several stakeholders that need different types of information related to the requirements.
Which stakeholder would need detailed technical interface requirements?
Correct Answer: D
Explanation
Implementation subject matter experts are the stakeholders who would need detailed technical interface requirements. These are the people who are responsible for designing, developing, and deploying the solution components that interact with other systems or applications. Technical interface requirements specify the format, structure, protocol, and security of the data exchange between the solution and the external entities.
Project manager, regulators, and testers are other types of stakeholders who may need different levels of information related to the requirements, but not necessarily the technical interface details. References:
BABOK Guide, p. 29, 36, 51, 54
CBAP / CCBA Certified Business Analysis Study Guide, p. 45, 49, 50, 52
Certified Business Analysis Professional (CBAP) | Coursera, Course 1, Week 3, Video: