Explanation/Reference:
Explanation:
Process: 6.1 Plan Schedule Management
Definition: The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.
Key Benefit: The key benefit of this process is that it provides guidance and direction on how the project schedule will be managed throughout the project.
Inputs
1. Project management plan
2. Project charter
3. Enterprise environmental factors
4. Organizational process assets
Tools & Techniques
1. Expert judgment
2. Analytical techniques
3. Meetings
Outputs
1. Schedule management plan
4.1.2.1 Expert Judgment
Expert judgment is often used to assess the inputs used to develop the project charter. Expert judgment is applied to all technical and management details during this process. Such expertise is provided by any group or individual with specialized knowledge or training and is available from many sources, including:
Other units within the organization,

Consultants,

Stakeholders, including customers or sponsors,

Professional and technical associations,

Industry groups,

Subject matter experts (SME), and

Project management office (PMO).