Which process involves subdividing project deliverables and project work into smaller, more manageable portions?
Correct Answer: B
Explanation/Reference: Explanation: Process: 5.4 Create WBS Definition: WBS is the process of subdividing project deliverables and project work into smaller, more manageable components. Key Benefit: The key benefit of this process is that it provides a structured vision of what has to be delivered. Inputs 1. Scope management plan 2. Project scope statement 3. Requirements documentation 4. Enterprise environmental factors 5. Organizational process assets Tools & Techniques 1. Decomposition 2. Expert judgment Outputs 1. Scope baseline 2. Project documents updates