Valid CAPM Dumps shared by EduDump.com for Helping Passing CAPM Exam! EduDump.com now offer the newest CAPM exam dumps, the EduDump.com CAPM exam questions have been updated and answers have been corrected get the newest EduDump.com CAPM dumps with Test Engine here:
Which tool or technique can a project manager use to select in advance a team member who will be crucial to the task?
Correct Answer: D
Explanation/Reference: Explanation: 9.2.2.1 Pre-assignment When project team members are selected in advance, they are considered pre-assigned. This situation can occur if the project is the result of specific people being identified as part of a competitive proposal, if the project is dependent upon the expertise of particular persons, or if some staff assignments are defined within the project charter.