Which input to the Manage Stakeholder Engagement process is used to document changes that occur during the project?
Correct Answer: B
Explanation/Reference:
Explanation:
4.5.3.2 Change Log
A change log is used to document changes that occur during a project. These changes and their impact to the project in terms of time, cost, and risk, are communicated to the appropriate stakeholders.
Rejected change requests are also captured in the change log.
13.3 Manage Stakeholder Engagement
Definition: The process of communicating and working with stakeholders to meet their needs/ expectations, address issues as they occur, and foster appropriate stakeholder engagement in project activities throughout the project life cycle.
Key Benefit: The key benefit of this process is that it allows the project manager to increase support and minimize resistance from stakeholders, significantly increasing the chances to achieve project success.
Inputs
1. Stakeholder management plan
2. Communications management plan
3. Change log
4. Organizational process assets
Tools & Techniques
1. Communication methods
2. Interpersonal skills
3. Management skills
Outputs
1. Issue log
2. Change requests
3. Project management plan updates
4. Project documents updates
5. Organizational process assets updates