Valid CAPM Dumps shared by ExamDiscuss.com for Helping Passing CAPM Exam! ExamDiscuss.com now offer the newest CAPM exam dumps, the ExamDiscuss.com CAPM exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com CAPM dumps with Test Engine here:
Which output is the approved version of the time-phased project budget?
Correct Answer: D
Explanation/Reference: Explanation: A project budget includes all the funds authorized to execute the project. The cost baseline is the approved version of the time-phased project budget, but excludes management reserves. 7.3.3.1 Cost Baseline The cost baseline is the approved version of the time-phased project budget, excluding any management reserves, which can only be changed through formal change control procedures and is used as a basis for comparison to actual results. It is developed as a summation of the approved budgets for the different schedule activities.