Valid CAPM Dumps shared by ExamDiscuss.com for Helping Passing CAPM Exam! ExamDiscuss.com now offer the newest CAPM exam dumps, the ExamDiscuss.com CAPM exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com CAPM dumps with Test Engine here:
The methodology that combines scope, schedule, and resource measurements to assess project performance and progress is known as:
Correct Answer: A
Explanation/Reference: Explanation: 7.4.2.1 Earned Value Management Earned value management (EVM) is a methodology that combines scope, schedule, and resource measurements to assess project performance and progress. It is a commonly used method of performance measurement for projects. It integrates the scope baseline with the cost baseline, along with the schedule baseline, to form the performance measurement baseline, which helps the project management team assess and measure project performance and progress. It is a project management technique that requires the formation of an integrated baseline against which performance can be measured for the duration of the project.