Explanation/Reference: Explanation: Process: 6.7 Control Schedule Definition: Control Schedule is the process of monitoring the status of project activities to update project progress and manage changes to the schedule baseline to achieve the plan. Key Benefit: The key benefit of this process is that it provides the means to recognize deviation from the plan and take corrective and preventive actions and thus minimize risk. Inputs 1. Project management plan 2. Project schedule 3. Work performance data 4. Project calendars 5. Schedule data 6. Organizational process assets Tools & Techniques 1. Performance reviews 2. Project management software 3. Resource optimization techniques 4. Modeling techniques 5. Leads and lags 6. Schedule compression 7. Scheduling tool Outputs 1. Work performance information 2. Schedule forecasts 3. Change requests 4. Project management plan updates 5. Project documents updates 6. Organizational process assets updates