A project manager managing a cross-cultural virtual project team across several time zones should be concerned about the impacts of which communication technology factor?
Correct Answer: C
Explanation/Reference: Explanation: Project environment. There is a need to determine if the team will meet and operate on a face-to-face basis or in a virtual environment; whether they will be located in one or multiple time zones; whether they will use multiple languages for communication; and finally, whether there are any other project environmental factors, such as culture, which may affect communications.