Enterprise environmental factors are an input to which process?
Correct Answer: C
Explanation/Reference: Explanation: Process: 5.1 Plan Scope Management Definition: The process of creating a scope management plan that documents how the project scope will be defined, validated, and controlled. Key Benefit: The key benefit of this process is that it provides guidance and direction on how scope will be managed throughout the project. Inputs 1. Project management plan 2. Project charter 3. Enterprise environmental factors 4. Organizational process assets Tools & Techniques 1. Expert judgment 2. Meetings Outputs Scope management plan Requirements management plan