Valid CAPM Dumps shared by ExamDiscuss.com for Helping Passing CAPM Exam! ExamDiscuss.com now offer the newest CAPM exam dumps, the ExamDiscuss.com CAPM exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com CAPM dumps with Test Engine here:
Explanation/Reference: Explanation: Process: 4.6. Close Project or Phase Definition: The process of finalizing all activities across all of the Project Management Process Groups to formally complete the phase or project. Key Benefit: The key benefit of this process is that it provides lessons learned, the formal ending of project work, and the release of organization resources to pursue new endeavors. Inputs 1. Project management plan 2. Accepted deliverables 3. Organizational process assets Tools & Techniques 1. Expert judgment 2. Analytical techniques 3. Meetings Outputs 1. Final product, service, or result transition 2. Organizational process assets updates