Valid CAPM Dumps shared by ExamDiscuss.com for Helping Passing CAPM Exam! ExamDiscuss.com now offer the newest CAPM exam dumps, the ExamDiscuss.com CAPM exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com CAPM dumps with Test Engine here:
Funding limit reconciliation is a tool and technique used in which process?
Correct Answer: B
Explanation/Reference: Explanation: 7.3.2.5 Funding Limit Reconciliation The expenditure of funds should be reconciled with any funding limits on the commitment of funds for the project. A variance between the funding limits and the planned expenditures will sometimes necessitate the rescheduling of work to level out the rate of expenditures. This is accomplished by placing imposed date constraints for work into the project schedule. Process: 7.3 Determine Budget Definition: The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline. Key Benefit: The key benefit of this process is that it determines the cost baseline against which project performance can be monitored and controlled. Inputs 1. Cost management plan 2. Scope baseline 3. Activity cost estimates 4. Basis of estimates 5. Project schedule 6. Resource calendars 7. Risk register 8. Agreements 9. Organizational process assets Tools & Techniques 1. Cost aggregation 2. Reserve analysis 3. Expert judgment 4. Historical relationships 5. Funding limit reconciliation Outputs 1. Cost baseline 2. Project funding requirements 3. Project documents updates