The Project Human Resource Management process that involves confirming human resource availability and obtaining the team necessary to complete project activities is:
Correct Answer: A
Explanation/Reference: Explanation: Process: 9.2 Acquire Project Team Definition: The process of confirming human resource availability and obtaining the team necessary to complete project activities. Key Benefit: The key benefit of this process consists of outlining and guiding the team selection and responsibility assignment to obtain a successful team. Inputs 1. Human resource management plan 2. Enterprise environmental factors 3. Organizational process assets Tools & Techniques 1. Pre-assignment 2. Negotiation 3. Acquisition 4. Virtual teams 5. Multi-criteria decision analysis Outputs 1. Project staff assignments 2. Resource calendars 3. Project management plan updates