Which process includes prioritizing risks for subsequent further analysis or action by assessing and combining their probability of occurrence and impact?
Correct Answer: A
Explanation/Reference: Explanation: Process: 11.3 Perform Qualitative Risk Analysis Definition: The process of prioritizing risks for further analysis or action by assessing and combining their probability of occurrence and impact. Key Benefit: The key benefit of this process is that it enables project managers to reduce the level of uncertainty and to focus on high-priority risks. Inputs 1. Risk management plan 2. Scope baseline 3. Risk register 4. Enterprise environmental factors 5. Organizational process assets Tools & Techniques 1. Risk probability and impact assessment 2. Probability and impact matrix 3. Risk data quality assessment 4. Risk categorization 5. Risk urgency assessment 6. Expert judgment Outputs 1. Project documents updates