Correct Answer: C
Explanation/Reference:
Explanation:
Knowledge Areas
1. 4. Project Integration Management
2. 5. Project Scope Management
3. 6. Project Time Management
4. 7. Project Cost Management
5. 8. Project Quality Management
6. 9. Project Human Resource Management
7. 10.Project Communications Management
8. 11.Project Risk Management
9. 12.Project Procurement Management
10.13.Project Stakeholder Management
Planning Process Group
4.2 Develop Project Management Plan
5.1 Plan Scope Management
5.2 Collect Requirements
5.3 Define Scope
5.4 Create WBS
6.1 Plan Schedule Management
6.2 Define Activities
6.3 Sequence Activities
6.4 Estimate Activity Resources
6.5 Estimate Activity Durations
6.6 Develop Schedule
7.1 Plan Cost Management
7.2 Estimate Costs
7.3 Determine Budget
8.1 Plan Quality Management
9.1 Plan Human Resource Management
10.1 Plan Communications Management
11.1 Plan Risk Management
11.2 Identify Risks
11.3 Perform Qualitative Risk Analysis
11.4 Perform Quantitative Risk Analysis
11.5 Plan Risk Responses
12.1 Plan Procurement Management
13.2 Plan Stakeholder Management